4/29/2024
|
Application pending.
|
|
4/29/2024
|
Application submitted by applicant.
|
|
5/3/2024
|
Point Review - Printed-Online Application
|
|
5/8/2024
|
Zoning Review - Reviewed
|
|
5/8/2024
|
Plan Review - Documents Required
|
|
5/13/2024
|
Plan Review - Documents Required
|
|
5/14/2024
|
Plan Review - Documents Required
|
|
5/15/2024
|
Plan Review - Documents Required
|
|
5/16/2024
|
Plan Review - Documents Required
|
|
5/22/2024
|
Plan Review - Documents Required
|
|
5/31/2024
|
Plan Review - Documents Required
|
|
6/4/2024
|
Plan Review - Documents Required
|
|
6/5/2024
|
Plan Review - Plumbing Approved
|
|
6/5/2024
|
Plan Review - Mechanical Approved
|
|
6/5/2024
|
Plan Review - Electrical Approved
|
|
6/5/2024
|
Plan Review - Building Approved
|
|
6/5/2024
|
Plan Review - Reviewed
|
|
6/5/2024
|
Final Review - Documents Required
|
|
6/7/2024
|
Final Review - Documents Required
|
|
6/10/2024
|
Final Review - Documents Required
|
|
6/12/2024
|
Final Review - Documents Required
|
|
6/17/2024
|
Final Review - Documents Required
|
|
6/17/2024
|
Final Review - Documents Required
|
|
6/25/2024
|
Final Review - Documents Required
|
|
7/2/2024
|
Final Review - Documents Required
|
|
7/9/2024
|
Final Review - Documents Required
|
|
7/23/2024
|
Final Review - Documents Required
|
|
7/30/2024
|
Final Review - Documents Required
|
|
7/30/2024
|
Final Review - Documents Required
|
|
8/1/2024
|
Final Review - Documents Required
|
|
8/2/2024
|
Final Review - Documents Required
|
|
8/14/2024
|
Final Review - Documents Required
|
|
8/19/2024
|
Final Review - Documents Required
|
|
8/19/2024
|
Final Review - Payment Needed
|
|
8/23/2024
|
Final Review - Payment Needed
|
|
8/26/2024
|
Permit Issued
|
|
6/6/2025
|
Final Review - Payment Needed
|
|
6/9/2025
|
Final Review - Payment Needed
|
|
6/12/2025
|
Final Review - Payment Needed
|
|
6/16/2025
|
Final Review - Payment Needed
|
|
6/21/2025
|
Final Review - Payment Needed
|
|
7/3/2025
|
Final Review - Payment Needed
|
|
7/10/2025
|
Permit Renewed
|