| Inspection |
Notes |
Performed By |
Date |
| Passed: Fire - Plan Review |
Appears All Setbacks Are Met At This Time. |
Cpt. Shane Overstreet |
7/15/2024 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Waste Pipe Only |
Matt Forsyth |
8/15/2024 |
| Passed: Building - Footer |
|
Troy Crews |
8/21/2024 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
8/21/2024 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
8/22/2024 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
8/22/2024 |
| Passed: Electrical - 2nd Rough-In |
Shop Area |
Troy Crews |
12/6/2024 |
| Passed: Building - Framing |
|
Troy Crews |
12/20/2024 |
| Failed: Electrical - 2nd Rough-In |
Not Complete |
Troy Crews |
12/20/2024 |
| Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
12/20/2024 |
| Passed: Building - Insulation |
|
Troy Crews |
12/20/2024 |
| Passed: Electrical - 2nd Rough-In |
2nd Flo9r Only |
Troy Crews |
12/27/2024 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
12/27/2024 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
12/31/2024 |
| Passed: Electrical - Above Ceiling |
|
Troy Crews |
2/13/2025 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
2/13/2025 |
| Failed: Electrical - Permanent Power |
Not Complete. Need As Built Approved By Architect Not Per Plan. Or As Built Prdpared By Electrician With Wire Sizes And Types. Check Ground For Proper Sizing. |
Troy Crews |
2/19/2025 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
2/20/2025 |
| Release to power company |
|
Troy Crews |
2/20/2025 |
| Passed: Building - Final |
Parking Lot To Be Completed And Inspected By County Engineer And City Release On Utilities(rec'd) Prior To Co -- 4.2.25 |
Troy Crews |
3/25/2025 |
| Passed: Fire - Fire Final |
|
Cpt. Shane Overstreet |
3/27/2025 |
| Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection |
|
City Of Lake City Distribution And Collections Department |
4/1/2025 |
| Passed: Engineering - Zoning Final |
|
Chad Williams |
4/4/2025 |