| Septic Release Inspection |
|
Health Dept |
7/11/2024 |
| Passed: Building - Spot Check |
|
Troy Crews |
12/31/2024 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
1/3/2025 |
| Failed: Building - Monolithic Slab |
Do Not See Monolithic Slab Choice On Plans, Also Interior Footings Not Installed. |
Troy Crews |
1/13/2025 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
1/13/2025 |
| Passed: Building - Slab |
Interior Footers Added And Termite Spray Touched Up. |
Troy Crews |
1/22/2025 |
| Passed: Building - Roof Decking |
|
Troy Crews |
3/25/2025 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
3/25/2025 |
| Passed: Building - Framing |
Windows Only |
Troy Crews |
5/19/2025 |
| Passed: Building - Framing |
|
Troy Crews |
7/3/2025 |
| Passed: Mechanical - Rough In |
Will Need To Box Around Flex Duct In Upper Bedroom |
Troy Crews |
7/3/2025 |
| Cancelled: Electrical - 1st Underground Rough–In |
|
Troy Crews |
7/3/2025 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
7/3/2025 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
7/3/2025 |
| Passed: Building - Insulation |
Ac Duct Is Still Outside Of The Wall Upstairs |
Troy Crews |
7/29/2025 |
| Passed: Mechanical - Rough In |
Duct On Second Floor Boxed In |
Troy Crews |
8/5/2025 |
| Release to power company |
|
Mgarber |
2/24/2026 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
2/24/2026 |
| Submitted Power Release through FPL Portal |
|
Ward, Emaleigh C. |
2/24/2026 |
| Passed: Building - Spot Check |
Owner Working On Stone Facade. |
Troy Crews |
8/24/2026 |