Permit Details

Permit Search

Permit

New Residential Construction

649 NW NOEGEL RD
LAKE CITY, FL 32055

Permit #
000050356
Application #
65834
Status Completed
  1. Submitted Jun 12, 2024
  2. Issued Feb 23, 2026
  3. Expires Apr 12, 2027
  4. Completed Oct 14, 2026

Property

Parcel #
02398-306
Owner
Pope Stanley, Rabsatt-pope Beverly
Acres
5.08
Subdivision
Fairfield Estates
Zoning
A-3
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Engineers Elevation Letter
Finished floor requirement
12 INCHES ABOVE EXISTING GRADE
Document receieved
Yes
Fema map number
12023C0260C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
3328
Total Area (Sqft)
4703
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0537
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.

Status & Review History

  1. Point Review - Reviewed
  2. Plan Review - Corrections Needed
  3. Zoning Review - Documents Required
  4. Plan Review - Plumbing Approved
  5. Plan Review - Mechanical Approved
  6. Plan Review - Electrical Approved
  7. Plan Review - Building Approved
  8. Plan Review - Reviewed
  9. Zoning Review - Reviewed
  10. Final Review - Documents Required
  11. Final Review - Documents Required
  12. Final Review - Documents Required
  13. Final Review - Processing
  14. Final Review - Reviewed
  15. Final Review - Payment Needed
  16. Permit Issued
  17. Permit Reissued
  18. Permit Status Update Notification
  19. Permit Reissued
  20. Permit Status Update Notification

Contractors

This is an owner-builder project.

Inspections

  1. Jul 11, 2024

    Septic Release Inspection

    Inspected by Health Dept

  2. Dec 31, 2024

    Passed: Building - Spot Check

    Inspected by Troy Crews

  3. Jan 3, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  4. Jan 13, 2025

    Failed: Building - Monolithic Slab

    Do Not See Monolithic Slab Choice On Plans, Also Interior Footings Not Installed.

    Inspected by Troy Crews

  5. Jan 13, 2025

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  6. Jan 22, 2025

    Passed: Building - Slab

    Interior Footers Added And Termite Spray Touched Up.

    Inspected by Troy Crews

  7. Mar 25, 2025

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  8. Mar 25, 2025

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  9. May 19, 2025

    Passed: Building - Framing

    Windows Only

    Inspected by Troy Crews

  10. Jul 3, 2025

    Passed: Building - Framing

    Inspected by Troy Crews

  11. Jul 3, 2025

    Passed: Mechanical - Rough In

    Will Need To Box Around Flex Duct In Upper Bedroom

    Inspected by Troy Crews

  12. Jul 3, 2025

    Cancelled: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  13. Jul 3, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  14. Jul 3, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  15. Jul 29, 2025

    Passed: Building - Insulation

    Ac Duct Is Still Outside Of The Wall Upstairs

    Inspected by Troy Crews

  16. Aug 5, 2025

    Passed: Mechanical - Rough In

    Duct On Second Floor Boxed In

    Inspected by Troy Crews

  17. Feb 24, 2026

    Release to power company

    Inspected by Mgarber

  18. Feb 24, 2026

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  19. Feb 24, 2026

    Submitted Power Release through FPL Portal

    Inspected by Ward, Emaleigh C.

  20. Aug 24, 2026

    Passed: Building - Spot Check

    Owner Working On Stone Facade.

    Inspected by Troy Crews

  21. Oct 13, 2026

    Cancelled: Building - Final

    Inspected by Tcrews

  22. Oct 14, 2026

    Passed: Building - Final

    Approved - All Requirements Met To Release Co-- 10.14.26 Mg

    Inspected by Troy Crews