5/1/2024
|
Application pending.
|
5/1/2024
|
Application submitted by applicant.
|
5/1/2024
|
Point Review - Printed-Online Application
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
5/6/2024
|
Zoning Review - Reviewed
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
5/6/2024
|
Plan Review - Electrical Approved
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
5/6/2024
|
Plan Review - Building Approved
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
5/6/2024
|
Plan Review - Reviewed
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
5/6/2024
|
Final Review - Corrections Needed
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
5/21/2024
|
Final Review - Corrections Needed
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
5/23/2024
|
Final Review - Corrections Needed
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
5/28/2024
|
Final Review - Corrections Needed
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
6/5/2024
|
Final Review - Contact the Building Dept
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
6/10/2024
|
Final Review - Contact the Building Dept
NEEDED
* OWNERS PHONE NUMBER
* LICENSE FOR ELECTRICIAN DOESNT BELONG TO CLAY METZGER - WE NEED LICESNE HOLDERS SIGNATURE ON SUB FORM OR AUTHORIZATION FOR CLAY TO SIGN SUB FORM
* ENGINEER CELL TO BE COMPLETED
* NOC DOES NOT MEET STATE STANDARDS PLEASE USE THE ONE AVAILABLE ON OUR WEBSITE
|
6/17/2024
|
Final Review - Reviewed
|
6/17/2024
|
Final Review - Payment Needed
|
6/17/2024
|
Permit Issued
Permit # created and approved from payment.
|