4/3/2024
|
Application pending.
|
6/3/2024
|
Application submitted by applicant.
|
6/4/2024
|
Point Review - Printed-Online Application
NEEDED
* OWNERS PHONE NUMBER
* ARCHITECT/ENGINEER CELL TO BE COMPLETED
* CONTRACTORS SIGNATURE IS MISSING ON OWNER AND CONTRACTOR SIGNATURE PAGE
* NOC WILL NEED TO BE RECORDED PRIOR TO INSPECTIONS BEING GRANTED
* CONTRACTOR AUTHORIZATION FOR SERGE CHVORUN
****PLEASE BE MINDFUL LAND OWNER AFFIDAVITS ARE NOT REQUIRED FROM OWNER TO CONTRACTOR THIS IS WHAT THE OWNER AND CONTRACTOR SIGNATURE PAGE IS FOR..........OWNER DISCLOSURE STATEMENTS ARE NOT REQUIRED WHEN A CONTRACTOR IS INVOLVED........IF THE PANELS ARE ROOF MOUNTED PLEASE DONT UPLOAD SOMETHING UNDER GROUND MOUNTED LOCATION****
|
6/7/2024
|
Zoning Review - Reviewed
NEEDED
* NOC WILL NEED TO BE RECORDED PRIOR TO INSPECTIONS BEING GRANTED
****PLEASE BE MINDFUL LAND OWNER AFFIDAVITS ARE NOT REQUIRED FROM OWNER TO CONTRACTOR THIS IS WHAT THE OWNER AND CONTRACTOR SIGNATURE PAGE IS FOR..........OWNER DISCLOSURE STATEMENTS ARE NOT REQUIRED WHEN A CONTRACTOR IS INVOLVED.
|
6/7/2024
|
Plan Review - Electrical Approved
NEEDED
* NOC WILL NEED TO BE RECORDED PRIOR TO INSPECTIONS BEING GRANTED
****PLEASE BE MINDFUL LAND OWNER AFFIDAVITS ARE NOT REQUIRED FROM OWNER TO CONTRACTOR THIS IS WHAT THE OWNER AND CONTRACTOR SIGNATURE PAGE IS FOR..........OWNER DISCLOSURE STATEMENTS ARE NOT REQUIRED WHEN A CONTRACTOR IS INVOLVED.
|
6/7/2024
|
Plan Review - Building Approved
NEEDED
* NOC WILL NEED TO BE RECORDED PRIOR TO INSPECTIONS BEING GRANTED
****PLEASE BE MINDFUL LAND OWNER AFFIDAVITS ARE NOT REQUIRED FROM OWNER TO CONTRACTOR THIS IS WHAT THE OWNER AND CONTRACTOR SIGNATURE PAGE IS FOR..........OWNER DISCLOSURE STATEMENTS ARE NOT REQUIRED WHEN A CONTRACTOR IS INVOLVED.
|
6/7/2024
|
Plan Review - Reviewed
NEEDED
* NOC WILL NEED TO BE RECORDED PRIOR TO INSPECTIONS BEING GRANTED
****PLEASE BE MINDFUL LAND OWNER AFFIDAVITS ARE NOT REQUIRED FROM OWNER TO CONTRACTOR THIS IS WHAT THE OWNER AND CONTRACTOR SIGNATURE PAGE IS FOR..........OWNER DISCLOSURE STATEMENTS ARE NOT REQUIRED WHEN A CONTRACTOR IS INVOLVED.
|
6/7/2024
|
Final Review - Documents Required
NEEDED
* NOC WILL NEED TO BE RECORDED PRIOR TO INSPECTIONS BEING GRANTED
****PLEASE BE MINDFUL LAND OWNER AFFIDAVITS ARE NOT REQUIRED FROM OWNER TO CONTRACTOR THIS IS WHAT THE OWNER AND CONTRACTOR SIGNATURE PAGE IS FOR..........OWNER DISCLOSURE STATEMENTS ARE NOT REQUIRED WHEN A CONTRACTOR IS INVOLVED.
|
6/11/2024
|
Permit Issued
Permit # created and approved from payment.
|