| 10/2/2023 |
Application pending. |
| 4/16/2024 |
Application submitted by applicant. |
| 4/16/2024 |
Point Review - Printed-Online Application |
| 4/16/2024 |
Point Review - Reviewed |
| 4/18/2024 |
Zoning Review - Reviewed |
| 4/18/2024 |
Plan Review - Electrical Approved |
| 4/18/2024 |
Plan Review - Building Approved |
| 4/18/2024 |
Final Review - Documents Required |
| 5/2/2024 |
Final Review - Documents Required |
| 5/9/2024 |
Final Review - Documents Required |
| 5/20/2024 |
Final Review - Documents Required |
| 5/21/2024 |
Final Review - Documents Required |
| 5/21/2024 |
Final Review - Contact the Building Dept |
| 5/23/2024 |
Final Review - Contact the Building Dept |
| 5/28/2024 |
Final Review - Contact the Building Dept |
| 6/4/2024 |
Final Review - Documents Required |
| 6/7/2024 |
Final Review - Payment Needed |
| 6/10/2024 |
Permit Issued |