1/26/2024
|
Application pending.
|
1/30/2024
|
Application submitted by applicant.
|
1/30/2024
|
City of Lake City Utilities Notified.
City of Lake City Notified of Application within Utility Service Areas LC_SEWER.
|
1/31/2024
|
Point Review - Printed-Online Application
NEEDED:
*OWNER AND CONTRACTOR SIGNATURE---- ONE UPLOADED IS BLANK, MUST HAVE OWNERS SIGNATURE AND CONTRACTORS NOTARIZED SIGNATURE
*SIGNED ELECTRICAL SUBFORM
|
1/31/2024
|
Point Review - Reviewed
NEEDED:
*OWNER AND CONTRACTOR SIGNATURE---- ONE UPLOADED IS BLANK, MUST HAVE OWNERS SIGNATURE AND CONTRACTORS NOTARIZED SIGNATURE
*SIGNED ELECTRICAL SUBFORM
|
1/31/2024
|
Plan Review - Electrical Approved
NEEDED:
*OWNER AND CONTRACTOR SIGNATURE---- ONE UPLOADED IS BLANK, MUST HAVE OWNERS SIGNATURE AND CONTRACTORS NOTARIZED SIGNATURE
*SIGNED ELECTRICAL SUBFORM
|
1/31/2024
|
Plan Review - Building Approved
NEEDED:
*OWNER AND CONTRACTOR SIGNATURE---- ONE UPLOADED IS BLANK, MUST HAVE OWNERS SIGNATURE AND CONTRACTORS NOTARIZED SIGNATURE
*SIGNED ELECTRICAL SUBFORM
|
1/31/2024
|
Plan Review - Reviewed
NEEDED:
*OWNER AND CONTRACTOR SIGNATURE---- ONE UPLOADED IS BLANK, MUST HAVE OWNERS SIGNATURE AND CONTRACTORS NOTARIZED SIGNATURE
*SIGNED ELECTRICAL SUBFORM
|
1/31/2024
|
Zoning Review - Reviewed
NEEDED:
*OWNER AND CONTRACTOR SIGNATURE---- ONE UPLOADED IS BLANK, MUST HAVE OWNERS SIGNATURE AND CONTRACTORS NOTARIZED SIGNATURE
*SIGNED ELECTRICAL SUBFORM
|
1/31/2024
|
Final Review - Documents Required
NEEDED:
*OWNER AND CONTRACTOR SIGNATURE---- ONE UPLOADED IS BLANK, MUST HAVE OWNERS SIGNATURE AND CONTRACTORS NOTARIZED SIGNATURE
*SIGNED ELECTRICAL SUBFORM
|
2/2/2024
|
Final Review - Documents Required
NEEDED:
*OWNER AND CONTRACTOR SIGNATURE---- ONE UPLOADED IS BLANK, MUST HAVE OWNERS SIGNATURE AND CONTRACTORS NOTARIZED SIGNATURE
*SIGNED ELECTRICAL SUBFORM
|
2/16/2024
|
Final Review - Processing
NEEDED:
|
3/20/2024
|
Final Review - Processing
NEEDED:
|
3/25/2024
|
Final Review - Payment Needed
|
4/1/2024
|
Final Review - Payment Needed
|
4/5/2024
|
Final Review - Payment Needed
|
4/12/2024
|
Final Review - Payment Needed
|
4/19/2024
|
Final Review - Payment Needed
|
4/26/2024
|
Final Review - Payment Needed
|
4/29/2024
|
Permit Issued
Permit # created and approved from payment.
|