Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Matt Forsyth |
6/24/2024 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
6/24/2024 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
7/31/2024 |
Release to power company |
|
Matt Forsyth |
7/31/2024 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
8/8/2024 |
Passed: Building - Slab |
|
Matt Forsyth |
8/19/2024 |
Passed: Engineering - Initial Driveway |
|
Smith, Blake |
9/13/2024 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
10/16/2024 |
Passed: Building - Framing |
Gable Horizontal Framing Member |
Matt Forsyth |
10/16/2024 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
10/16/2024 |
Passed: Building - Strapping |
|
Matt Forsyth |
10/16/2024 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
10/16/2024 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
11/22/2024 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
11/22/2024 |
Failed: Plumbing/Gas - 2nd Rough-In |
Standpipe For Washing Machine Is Too Low. |
Matt Forsyth |
11/22/2024 |
Passed: Building - Insulation |
|
Matt Forsyth |
12/6/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
Standpoint Was Raised Countertop Will Be Over The Top Of The Washing Machine |
Matt Forsyth |
12/6/2024 |
Passed: Electrical - Permanent Power |
Request Septic Release |
Matt Forsyth |
2/13/2025 |
Septic Release Inspection |
Pending Final Drive To Release Pwr |
Health Dept |
2/28/2025 |
Release to power company |
Rec'd Drive And Septic |
Matt Forsyth |
3/3/2025 |
Passed: Engineering - Final Driveway |
|
Beach, Garrett |
3/3/2025 |
Submitted Power Release through FPL Portal |
|
Garber, Melissa |
3/3/2025 |
Certificate-Release Certificate |
Docs Rec'd |
Matt Forsyth |
4/16/2025 |
Passed: Building - Final |
Cannot Closed Permit Or Release Certificate Of Occupancy Due To Missing Required Documents. |
Matt Forsyth |
4/16/2025 |