Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Beach, Garrett |
4/11/2024 |
Passed: Electrical - Temporary Service |
|
Anthony Aslan |
5/17/2024 |
Release to power company |
|
Anthony Aslan |
5/17/2024 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
5/29/2024 |
Passed: Building - Monolithic Slab |
Need Picture Of Bonding Wire |
Anthony Aslan |
6/7/2024 |
Passed: Engineering - Setbacks |
Appears To Be Within Setbacks |
Anthony Aslan |
6/7/2024 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
6/26/2024 |
Passed: Building - Wall Sheathing |
|
Anthony Aslan |
6/26/2024 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Gary Pitzer |
7/30/2024 |
Passed: Building - Framing |
|
Gary Pitzer |
7/30/2024 |
Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
7/30/2024 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
Tub Flooded |
Gary Pitzer |
7/30/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Gary Pitzer |
7/30/2024 |
Passed: Mechanical - Rough In |
|
Gary Pitzer |
7/30/2024 |
Passed: Building - Insulation |
Walls And Ceiling Batts |
Gary Pitzer |
8/20/2024 |
Failed: Electrical - Permanent Power |
Missing Power Wire From Meter, Panel Wire Not Landed Outside Missing Dead Cover And Panel Cover. Outlet Covers Missing On Some |
Anthony Aslan |
11/7/2024 |
Passed: Electrical - Permanent Power |
Corrections Made
need Septic Release |
Anthony Aslan |
11/7/2024 |
Release to power company |
|
Melissa Garber |
12/12/2024 |
Septic Release Inspection |
|
Health Dept |
12/12/2024 |
Passed: Engineering - Initial Driveway |
|
Smith, Blake |
1/3/2025 |
Passed: Building - Final |
Cannot Closed Permit Or Release Certificate Of Occupancy Due To Missing Required Documents. |
Anthony Aslan |
1/22/2025 |
Certificate-Release Certificate |
|
Anthony Aslan |
1/24/2025 |