Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Anthony Aslan |
4/29/2024 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
4/29/2024 |
Passed: Electrical - Temporary Service |
|
Anthony Aslan |
5/8/2024 |
Release to power company |
|
Anthony Aslan |
5/8/2024 |
Passed: Building - Vertical Cells/Columns |
|
Anthony Aslan |
5/14/2024 |
Cancelled: Building - Slab |
|
Anthony Aslan |
5/14/2024 |
Failed: Building - Ext Strapping/Wall Sheathing |
No Floor Joist Inspection, Need Strapping Verified
incomplete Wall Sheathing, Wall Sheathing Nails Sunk In Steathing, Needs To Be Renailed And Head Flush With Surfaces
all Seams Need To Be Blocked Or Stud Added |
Anthony Aslan |
8/13/2024 |
Passed: Building - Ext Strapping/Wall Sheathing |
Corrections Made, Sending Pictures Of Side & Back Post |
Anthony Aslan |
8/20/2024 |
Failed: Building - Framing |
Many Issues |
Anthony Aslan |
9/9/2024 |
Passed: Building - Framing |
|
Anthony Aslan |
9/12/2024 |
Septic Release Inspection |
|
Health Dept |
1/15/2025 |
Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
1/28/2025 |
Passed: Mechanical - Rough In |
|
Anthony Aslan |
1/28/2025 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
1/28/2025 |
Failed: Building - Insulation |
Voids In Insulation In Several Places, End Of Headers Need Sealed Also Voids Between Studs, All Corners Missing Insulation And Behind Interior Walls The Intersect Exterior Walls, Insulation Protruding From Walls, Wiring Damaged When Removing Exterior Wall Insulation, Please Reschedule For Another Inspection Once These Problems Are Completed |
Gary Pitzer |
4/17/2025 |
Passed: Building - Insulation |
Corrections Made |
Anthony Aslan |
4/22/2025 |