Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Matt Forsyth |
4/19/2024 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
4/19/2024 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
5/28/2024 |
Passed: Building - Slab |
|
Matt Forsyth |
6/10/2024 |
Passed: Building - Lintel/Tie Beam |
|
Matt Forsyth |
6/24/2024 |
Passed: Building - Masonry Wall Reinforcing |
|
Matt Forsyth |
6/24/2024 |
Passed: Building - Vertical Cells/Columns |
|
Matt Forsyth |
6/24/2024 |
Rescheduled 7/17/2024:Building - Wall Sheathing |
|
Emaleigh Williams |
7/15/2024 |
Passed: Building - Wall Sheathing |
This Inspection Was A Partial Roof Inspection To Get Some Coverage Will Need Another Roof Sheathing Inspection For The Front Alright |
Matt Forsyth |
7/17/2024 |
Failed: Building - Framing |
Draft Stop Blocking Required In Closet Soffit Drop |
Matt Forsyth |
9/6/2024 |
Failed: Electrical - 2nd Rough-In |
Receptacles Are Required On Front And Back Porches |
Matt Forsyth |
9/6/2024 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
9/6/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
Water Spigots Loose In Block Wall |
Matt Forsyth |
9/6/2024 |
Passed: Building - Insulation |
|
Matt Forsyth |
10/1/2024 |
Passed: Electrical - Permanent Power |
Electrical Trim Out Complete |
Matt Forsyth |
2/12/2025 |
Release to power company |
|
Matt Forsyth |
2/12/2025 |
Failed: Building - Final |
Need Septic Release And Final Termite Treatment Documents |
Matt Forsyth |
2/13/2025 |
Septic Release Inspection |
|
Health Dept |
2/28/2025 |
Certificate-Release Certificate |
Rec'd Docs |
Emaleigh Williams |
3/3/2025 |
Passed: Building - Final |
Cannot Closed Permit Or Release Certificate Of Occupancy Due To Missing Required Documents. |
Matt Forsyth |
3/3/2025 |