8/17/2023
|
Application pending.
|
9/8/2023
|
Application submitted by applicant.
|
9/13/2023
|
Point Review - On Hold-Incomplete
NEEDED
* SEALED BUILDING PLANS
* SITE PLAN SHOWING DISTANCES FROM ALL 4 PROPERTY LINES TO PROPOSED BUILDING
* OWNER AND CONTRACTOR SIGNATURE PAGE - OWNER SIGNATURE MUST BE WETSIGNATURE OR DOCUSIGNED - FONTS NOT ACCCEPTED
* OWNER DISCLOSURE STATEMENT
|
9/20/2023
|
Point Review - Printed-Online Application
NEEDED
*APPLICANT MUST BE CONTRACTOR OR AUTHORIZED AGENT, NOT PROPERTY OWNER
*NEW SLAB, EXISTING SLAB, OR NO SLAB?
*PRODUCT APPROVAL CODES-- THEY ARE NOT ON PLANS
|
9/20/2023
|
Point Review - Reviewed
NEEDED
*APPLICANT MUST BE CONTRACTOR OR AUTHORIZED AGENT, NOT PROPERTY OWNER
*NEW SLAB, EXISTING SLAB, OR NO SLAB?
*PRODUCT APPROVAL CODES-- THEY ARE NOT ON PLANS
*ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
|
9/25/2023
|
Plan Review - Reviewed
NEEDED
*APPLICANT MUST BE CONTRACTOR OR AUTHORIZED AGENT, NOT PROPERTY OWNER
*ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
|
9/27/2023
|
Zoning Review - Reviewed
NEEDED
*APPLICANT MUST BE CONTRACTOR OR AUTHORIZED AGENT, NOT PROPERTY OWNER
** 1' RISE CERTIFICATE
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
|
10/3/2023
|
Final Review - Corrections Needed
NEEDED
*APPLICANT MUST BE CONTRACTOR OR AUTHORIZED AGENT, NOT PROPERTY OWNER
** 1' RISE CERTIFICATE
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
|
10/24/2023
|
Final Review - Corrections Needed
NEEDED
*APPLICANT MUST BE CONTRACTOR OR AUTHORIZED AGENT, NOT PROPERTY OWNER
** 1' RISE CERTIFICATE
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
|
11/8/2023
|
Final Review - Corrections Needed
NEEDED
*APPLICANT MUST BE CONTRACTOR OR AUTHORIZED AGENT, NOT PROPERTY OWNER
*OWNERS PHONE NUMBER
** 1' RISE CERTIFICATE
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
|
11/28/2023
|
Final Review - Corrections Needed
NEEDED
*APPLICANT PHONE NUMBER
* AUTHORIZATION FORM FOR ERICA RAMIREZ
** 1' RISE CERTIFICATE
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
|
12/1/2023
|
Final Review - Corrections Needed
NEEDED
** 1' RISE CERTIFICATE- STILL NEEDED-- WHAT WAS UPLOADED IS NOT CORRECT
*ENV HEALTH APPROVAL-- REQUIRED WITH ALL NEW STRUCTURES, REGARDLESS OF SEPTIC THERE OR NOT-- CONTACT 386-758-1058
*ESTIMATED COST OF CONSTRUCTION
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
|
12/7/2023
|
Final Review - Corrections Needed
NEEDED
** 1' RISE CERTIFICATE- STILL NEEDED-- WHAT WAS UPLOADED IS NOT CORRECT
*ENV HEALTH APPROVAL-- REQUIRED WITH ALL NEW STRUCTURES, REGARDLESS OF SEPTIC THERE OR NOT-- CONTACT 386-758-1058
*ESTIMATED COST OF CONSTRUCTION
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
|
1/31/2024
|
Final Review - Corrections Needed
NEEDED
** 1' RISE CERTIFICATE- STILL NEEDED-- WHAT WAS UPLOADED IS NOT CORRECT
*ENV HEALTH APPROVAL-- REQUIRED WITH ALL NEW STRUCTURES, REGARDLESS OF SEPTIC THERE OR NOT-- CONTACT 386-758-1058
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
***MG SPOKE WITH ERICA, APPLICATION STILL ACTIVE 1/2/2024***
|
2/27/2024
|
Final Review - Corrections Needed
NEEDED
** 1' RISE CERTIFICATE- STILL NEEDED-- WHAT WAS UPLOADED IS NOT CORRECT
*ENV HEALTH APPROVAL-- REQUIRED WITH ALL NEW STRUCTURES, REGARDLESS OF SEPTIC THERE OR NOT-- CONTACT 386-758-1058
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
***MG SPOKE WITH ERICA, APPLICATION STILL ACTIVE 1/2/2024***
|
3/8/2024
|
Final Review - Corrections Needed
NEEDED
** 1' RISE CERTIFICATE- STILL NEEDED-- WHAT WAS UPLOADED IS NOT CORRECT
*ENV HEALTH APPROVAL-- REQUIRED WITH ALL NEW STRUCTURES, REGARDLESS OF SEPTIC THERE OR NOT-- CONTACT 386-758-1058
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
***MG SPOKE WITH ERICA, APPLICATION STILL ACTIVE 1/2/2024***
|
3/14/2024
|
Final Review - Documents Required
NEEDED
*ENV HEALTH APPROVAL-- REQUIRED WITH ALL NEW STRUCTURES, REGARDLESS OF SEPTIC THERE OR NOT-- CONTACT 386-758-1058
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
ONE FOOT RISE RECIEVED
|
3/19/2024
|
Final Review - Documents Required
NEEDED
*ENV HEALTH APPROVAL-- REQUIRED WITH ALL NEW STRUCTURES, REGARDLESS OF SEPTIC THERE OR NOT-- CONTACT 386-758-1058
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
ONE FOOT RISE RECIEVED
|
3/19/2024
|
Final Review - Payment Needed
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
ONE FOOT RISE RECIEVED
|
3/19/2024
|
Permit Issued
Permit # created and approved from payment.
|
12/6/2024
|
Final Review - Payment Needed
**A CURRENT ELEVATION CERTIFICATE WILL BE REQUIRED PRIOR TO FINAL
** FFE SHALL BE ONE FOOT ABOVE THE BASE FLOOD ELEVATION OR THE STRUCTURE MUST HAVE ENGINEERED FLOOD VENTS
ONE FOOT RISE RECIEVED
|