12/19/2023
|
Point Review - Reviewed
NEEDED
* GLENWOOD KING UPDATED WORKERS COMP AND WORKERS COMP EXEMPTION
* ESTIMATED COST OF CONSTRUCTION
* CLARIFICATION IF THERE IS GOING TO BE PLUMBING AND MECHANICAL ADDED - SCOPE OF WORK DOES NOT INDICATE THERE WILL BE BUT WE WERE PROVIDED WITH SUB FORMS FOR EACH TRADE
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
|
12/20/2023
|
Plan Review - Reviewed
NEEDED
* GLENWOOD KING UPDATED WORKERS COMP AND WORKERS COMP EXEMPTION
* ESTIMATED COST OF CONSTRUCTION
* CLARIFICATION IF THERE IS GOING TO BE PLUMBING AND MECHANICAL ADDED - SCOPE OF WORK DOES NOT INDICATE THERE WILL BE BUT WE WERE PROVIDED WITH SUB FORMS FOR EACH TRADE
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
|
12/28/2023
|
Zoning Review - Documents Required
NEEDED
* GLENWOOD KING UPDATED WORKERS COMP AND WORKERS COMP EXEMPTION
* ESTIMATED COST OF CONSTRUCTION
* CLARIFICATION IF THERE IS GOING TO BE PLUMBING AND MECHANICAL ADDED - SCOPE OF WORK DOES NOT INDICATE THERE WILL BE BUT WE WERE PROVIDED WITH SUB FORMS FOR EACH TRADE
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
|
1/2/2024
|
Zoning Review - Documents Required
NEEDED
* GLENWOOD KING UPDATED WORKERS COMP AND WORKERS COMP EXEMPTION
* ESTIMATED COST OF CONSTRUCTION
* CLARIFICATION IF THERE IS GOING TO BE PLUMBING AND MECHANICAL ADDED - SCOPE OF WORK DOES NOT INDICATE THERE WILL BE BUT WE WERE PROVIDED WITH SUB FORMS FOR EACH TRADE
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
NEED SITE PLAN FOR LOCATION
|
1/12/2024
|
Zoning Review - Documents Required
NEEDED
* ESTIMATED COST OF CONSTRUCTION
*ENV HEALTH SIGNED SITE PLAN APPROVAL
* CLARIFICATION IF THERE IS GOING TO BE PLUMBING AND MECHANICAL ADDED - SCOPE OF WORK DOES NOT INDICATE THERE WILL BE BUT WE WERE PROVIDED
*EN WITH SUB FORMS FOR EACH TRADE
*POWER COMPANY
*NEED SITE PLAN FOR LOCATION
|
1/31/2024
|
Zoning Review - Documents Required
NEEDED
* ESTIMATED COST OF CONSTRUCTION
*ENV HEALTH SIGNED SITE PLAN APPROVAL
* CLARIFICATION IF THERE IS GOING TO BE PLUMBING AND MECHANICAL ADDED - SCOPE OF WORK DOES NOT INDICATE THERE WILL BE BUT WE WERE PROVIDED
*EN WITH SUB FORMS FOR EACH TRADE
*POWER COMPANY
*NEED SITE PLAN FOR LOCATION
|
2/2/2024
|
Zoning Review - Reviewed
NEEDED
* ESTIMATED COST OF CONSTRUCTION
*ENV HEALTH SIGNED SITE PLAN APPROVAL
* CLARIFICATION IF THERE IS GOING TO BE PLUMBING AND MECHANICAL ADDED - SCOPE OF WORK DOES NOT INDICATE THERE WILL BE BUT WE WERE PROVIDED WITH SUB FORMS FOR EACH TRADE
|
2/2/2024
|
Final Review - Documents Required
NEEDED
* ESTIMATED COST OF CONSTRUCTION
*ENV HEALTH SIGNED SITE PLAN APPROVAL
* CLARIFICATION IF THERE IS GOING TO BE PLUMBING AND MECHANICAL ADDED - SCOPE OF WORK DOES NOT INDICATE THERE WILL BE BUT WE WERE PROVIDED WITH SUB FORMS FOR EACH TRADE
|
2/13/2024
|
Final Review - Documents Required
NEEDED:
*MANUAL J REQUIRED
*ENV HEALTH SIGNED SITE PLAN APPROVAL
**PERMIT WILL BE ISSUED AS NON HABITABLE
|
2/19/2024
|
Final Review - Documents Required
NEEDED:
*MANUAL J REQUIRED
*ENV HEALTH SIGNED SITE PLAN APPROVAL
**PERMIT WILL BE ISSUED AS NON HABITABLE
|
2/28/2024
|
Final Review - Documents Required
NEEDED:
*MANUAL J REQUIRED
*ENV HEALTH SIGNED SITE PLAN APPROVAL
**PERMIT WILL BE ISSUED AS NON HABITABLE
|
3/4/2024
|
Final Review - Documents Required
NEEDED:
*ENV HEALTH SIGNED SITE PLAN APPROVAL
**PERMIT WILL BE ISSUED AS NON HABITABLE
|
3/5/2024
|
Final Review - Documents Required
NEEDED:
*ENV HEALTH SIGNED SITE PLAN APPROVAL
**PERMIT WILL BE ISSUED AS NON HABITABLE
MANUAL J RECEIVED
|
3/15/2024
|
Final Review - Payment Needed
**PERMIT WILL BE ISSUED AS NON HABITABLE
MANUAL J RECEIVED
|
3/18/2024
|
Permit Issued
Permit #000049450 created and approved.
|
2/24/2025
|
Permit Reissued
Permit reissued to reflect updated information.
|