Inspection |
Notes |
Performed By |
Date |
Failed: Engineering - Initial Driveway |
This Is A Private Road. |
Beach, Garrett |
3/18/2024 |
Electrical -1st Underground Rough–In |
Electric Steel Bond |
Gary Pitzer |
4/2/2024 |
Passed: Engineering - Setbacks |
|
Gary Pitzer |
4/2/2024 |
Passed: Building - Footer |
2#5 Wired On Chairs |
Gary Pitzer |
4/2/2024 |
Passed: Electrical - Temporary Service |
Service With One Gfci Outlet |
Gary Pitzer |
4/9/2024 |
Release to power company |
|
Gary Pitzer |
4/9/2024 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
4/30/2024 |
Passed: Building - Monolithic Slab |
Porches House |
Anthony Aslan |
5/7/2024 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
5/7/2024 |
Passed: Building - Slab |
Main House Slab |
Anthony Aslan |
5/7/2024 |
Passed: Building - Monolithic Slab |
Hanger Slab |
Anthony Aslan |
5/21/2024 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
5/21/2024 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
6/21/2024 |
Passed: Building - Wall Sheathing |
|
Anthony Aslan |
6/21/2024 |
Passed: Building - Framing |
|
Anthony Aslan |
7/2/2024 |
Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
7/19/2024 |
Passed: Mechanical - Rough In |
|
Anthony Aslan |
7/19/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
7/19/2024 |
Passed: Building - Insulation |
Walls Batts R13 |
Gary Pitzer |
7/23/2024 |
Septic Release Inspection |
|
Health Dept |
10/30/2024 |
Failed: Electrical - Permanent Power |
1. Support Conduits Under Panel, 2. Ko Seal In Exterior Disconnect, Bonding Screw |
Gary Pitzer |
11/15/2024 |
Passed: Electrical - Permanent Power |
|
Anthony Aslan |
11/19/2024 |
Release to power company |
|
Anthony Aslan |
11/19/2024 |
Passed: Building - Final |
Cannot Closed Permit Or Release Certificate Of Occupancy Due To Missing Required Documents. |
Anthony Aslan |
12/18/2024 |
Certificate-Release Certificate |
Received Documents |
Anthony Aslan |
12/19/2024 |