Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 2nd Rough-In |
First Rough Slab |
Troy Crews |
3/1/2024 |
Cancelled: Building - Slab |
|
Neonta Anderson |
3/5/2024 |
Passed: Building - Slab |
|
Anthony Aslan |
3/7/2024 |
Septic Release Inspection |
|
Health Dept |
3/27/2024 |
Passed: Building - Vertical Cells/Columns |
|
Anthony Aslan |
4/22/2024 |
Passed: Building - Lintel/Tie Beam |
Need Pictures Of Rebar Tied |
Anthony Aslan |
4/26/2024 |
Passed: Building - Masonry Wall Reinforcing |
Outside Walls |
Anthony Aslan |
5/6/2024 |
Passed: Building - Vertical Cells/Columns |
Outside Walls |
Anthony Aslan |
5/6/2024 |
Passed: Building - Lintel/Tie Beam |
Top Complete |
Anthony Aslan |
5/9/2024 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
5/13/2024 |
Passed: Building - Framing |
|
Anthony Aslan |
5/13/2024 |
Passed: Electrical - Above Ceiling |
|
Troy Crews |
5/22/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
5/28/2024 |
Passed: Mechanical - Rough In |
Piping To Fans Need Strapping |
Anthony Aslan |
5/29/2024 |
Passed: Building - Roof Decking |
|
Troy Crews |
6/10/2024 |
Cancelled: Building - Insulation |
|
Emaleigh Williams |
6/17/2024 |
Failed: Electrical - Permanent Power |
Job Site Locked Also Need Doors On Building For Permanent Power |
Troy Crews |
6/18/2024 |
Failed: Building - Insulation |
Job Site Lock |
Troy Crews |
6/18/2024 |
Passed: Building - Insulation |
|
Troy Crews |
6/21/2024 |
Passed: Electrical - Permanent Power |
Contractor To Install Door On Electric Room And Electrician To Keep Circuits Off Until Complete. |
Troy Crews |
6/21/2024 |
Release to power company |
|
Troy Crews |
6/21/2024 |
Passed: Plumbing/Gas - Sanitary |
Connection Was For Under The Road Final Connection Next To Clean Out Not Completed |
Matt Forsyth |
6/25/2024 |
Passed: Plumbing/Gas - Water Pipe |
Water Has Been Under The Road To Lift Station Final Connection To Hydrant Has Not Been Made |
Matt Forsyth |
6/25/2024 |
Release to power company |
Resending Due To Pwr Company Not Receiving
|
Troy Crews |
6/27/2024 |
Failed: Electrical - Permanent Power |
Job Site Locked Up 4:01pm |
Troy Crews |
8/1/2024 |
Cancelled: Electrical - Permanent Power |
|
Emaleigh Williams |
8/2/2024 |
Rescheduled 8/7/2024:Electrical - Permanent Power |
|
Troy Crews |
8/6/2024 |
Passed: Electrical - Permanent Power |
Above Ceiling Also |
Troy Crews |
8/7/2024 |
Release to power company |
|
Troy Crews |
8/7/2024 |
Passed: Electrical - Above Ceiling |
|
Troy Crews |
8/7/2024 |
Passed: Building - Final |
|
Troy Crews |
8/19/2024 |