Inspection |
Notes |
Performed By |
Date |
Rescheduled 1/5/2024:Building - Footer |
|
Gary Pitzer |
1/4/2024 |
Rescheduled 1/5/2024:Engineering - Setbacks |
|
Gary Pitzer |
1/4/2024 |
Passed: Engineering - Setbacks |
|
Gary Pitzer |
1/4/2024 |
Passed: Building - Footer |
|
Gary Pitzer |
1/4/2024 |
Electrical -1st Underground Rough–In |
Under Slab Conduits |
Gary Pitzer |
2/1/2024 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Dvw Only |
Gary Pitzer |
2/1/2024 |
Passed: Building - Slab |
Plastic,tape,wire And Steel |
Gary Pitzer |
2/7/2024 |
Passed: Building - Masonry Wall Reinforcing |
Steel In Walls And Bond Beams, Wired At Bottom And Top |
Gary Pitzer |
3/11/2024 |
Cancelled: Building - Roof Decking |
|
Gary Pitzer |
3/27/2024 |
Passed: Building - Roof Decking |
|
Gary Pitzer |
3/27/2024 |
Passed: Building - Framing |
|
Gary Pitzer |
3/27/2024 |
Cancelled: Engineering - Setbacks |
|
Gary Pitzer |
4/2/2024 |
Cancelled: Building - Footer |
|
Gary Pitzer |
4/2/2024 |
Passed: Building - Insulation |
Foam On Block Walls Only |
Gary Pitzer |
4/25/2024 |
Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
4/25/2024 |
Passed: Mechanical - Rough In |
|
Gary Pitzer |
4/25/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Gary Pitzer |
4/25/2024 |
Septic Release Inspection |
|
Health Dept |
8/14/2024 |
Passed: Electrical - Permanent Power |
|
Gary Pitzer |
8/14/2024 |
Release to power company |
|
Gary Pitzer |
8/14/2024 |
Failed: Building - Final |
1. Need Disconnects On Air Handlers And Water Heater, 2. Anti-siphon Devices On Threaded Hose Bibs |
Gary Pitzer |
10/21/2024 |
Passed: Building - Final |
Cannot Closed Permit Or Release Certificate Of Occupancy Due To Missing Required Documents. |
Gary Pitzer |
10/22/2024 |
Certificate-Release Certificate |
|
Gary Pitzer |
10/25/2024 |