Permit Details

Permit Search

Permit

New Residential Construction

234 SW CHERRY BLOSSOM WAY
LAKE CITY, FL 32024

Permit #
000048837
Application #
63121
Status Completed
  1. Submitted Nov 8, 2023
  2. Issued Dec 12, 2023
  3. Expires Sep 23, 2025
  4. Completed Jan 29, 2025

Property

Parcel #
03011-124
Owner
Gator Land Development, Llc,
Acres
0.48
Subdivision
Rose Pointe
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Subdivision Plat
Finished floor requirement
105'
Requirement needed
By Nailing Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
Yes
Fema map number
12023C0289D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
1596
Total Area (Sqft)
2225
Building Height
12
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
23-0805
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a minimum 4-inch wide strip of selfadhering polymer-modified bitumen complying with ASTM D1970 or a minimum 3 ¾ - inch wide strip of selfadhering flexible flashing tape complying with AAMA 711, applied over all joints in the roof decking. A felt underlayment complying with ASTM D226 Type II, ASTM D4869 Type Ill or IV, or ASTM D6757, or a synthetic underlayment meeting the performance requirements specified, is required to be applied over the strips/tape over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified
  4. Point Review - Printed-Online Application
  5. Plan Review - Documents Required
  6. Plan Review - Building Approved
  7. Plan Review - Electrical Approved
  8. Plan Review - Mechanical Approved
  9. Plan Review - Plumbing Approved
  10. Plan Review - Fuel/Gas Approved
  11. Plan Review - Reviewed
  12. Zoning Review - Reviewed
  13. Final Review - Reviewed
  14. Final Review - Payment Needed
  15. Permit Issued
  16. Final Review - Payment Needed

Contractors

  • Joseph C Peurrung

    Benchmark Builders Llc

    License
    CBC1259347
    Title
    Cert. Building
    Role
    Contractor
  • Benjamin T Keeler

    Keeler Roofing, Llc

    License
    CCC1330509
    Title
    Cert. Roofing
    Role
    Subcontractor
  • Marcus Matthews

    Matthews Electric Llc

    License
    EC13005459
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Robert Jarvis

    Jarvis Heat And Air Llc

    License
    CAC1816766
    Title
    Class "b" A/c
    Role
    Subcontractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor

Inspections

  1. Jan 4, 2024

    Passed: Building - Footer

    Inspected by Matt Forsyth

  2. Jan 4, 2024

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  3. Feb 22, 2024

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Matt Forsyth

  4. Mar 5, 2024

    Passed: Building - Slab

    Inspected by Matt Forsyth

  5. Apr 26, 2024

    Passed: Building - Framing

    Inspected by Matt Forsyth

  6. Apr 26, 2024

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  7. Apr 26, 2024

    Passed: Building - Strapping

    Inspected by Matt Forsyth

  8. Apr 26, 2024

    Passed: Building - Wall Sheathing

    Inspected by Matt Forsyth

  9. Jun 13, 2024

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  10. Jun 13, 2024

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  11. Jun 13, 2024

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  12. Jun 17, 2024

    Passed: Building - Insulation

    Inspected by Matt Forsyth

  13. Jan 8, 2025

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Matt Forsyth

  14. Jan 10, 2025

    Release to power company

    Inspected by Melissa Garber

  15. Jan 10, 2025

    Septic Release Inspection

    Inspected by Health Dept

  16. Jan 24, 2025

    Failed: Building - Final

    20 Amp Over Current Protection Required For Bathrooms And Garage

    Inspected by Matt Forsyth

  17. Jan 29, 2025

    Passed: Building - Final

    Items Addressed

    Inspected by Matt Forsyth

  18. Mar 27, 2025

    Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection

    Inspected by City Of Lake City Distribution And Collections Department

Documents