| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
1/11/2024 |
| Passed: Building - Monolithic Slab |
|
Anthony Aslan |
1/23/2024 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
1/23/2024 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
2/8/2024 |
| Passed: Building - Strapping |
|
Anthony Aslan |
2/8/2024 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
2/8/2024 |
| Failed: Plumbing/Gas - 2nd Rough-In |
No Pressure On Piping |
Anthony Aslan |
2/20/2024 |
| Passed: Electrical - 2nd Rough-In |
One Box In Kitchen Not Made Up, Check At Mechanicial Rough |
Anthony Aslan |
2/20/2024 |
| Passed: Mechanical - Rough In |
|
Anthony Aslan |
2/22/2024 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Tub Drop In, Shower Pan Good |
Anthony Aslan |
2/22/2024 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
No Water In System |
Anthony Aslan |
2/22/2024 |
| Passed: Building - Insulation |
Walls Only |
Anthony Aslan |
2/27/2024 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
2/27/2024 |
| Passed: Electrical - Permanent Power |
Need Septic Release |
Anthony Aslan |
4/30/2024 |
| Release to power company |
Rec'd Septic |
Anthony Aslan |
5/14/2024 |
| Septic Release Inspection |
|
Health Dept |
5/14/2024 |
| Passed: Building - Final |
Locking Caps A/c |
Anthony Aslan |
6/10/2024 |