Permit Details

Permit Search

Permit

New Residential Construction

950 SW NEWARK DR
FORT WHITE, FL 32038

Permit #
000048775
Application #
58814
Status Permit Issued This permit expired on Jun 1, 2024.
  1. Submitted Jan 25, 2023
  2. Issued Dec 4, 2023
  3. Expires Jun 1, 2024
  4. Completed —

Property

Parcel #
01229-000
Owner
Macke Jim
Acres
2.75
Subdivision
Three Rivers Estates Unit 19
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Permit Issued
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0459C
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
480
Total Area (Sqft)
696
Building Height
10
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
23-0236
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
Other (explain)
Sealed roof decking explanation for other option.
metal roof 30# felt paper osb plywood

Status & Review History

  1. Point Review - Reviewed
  2. Point Review - Printed-Online Application
  3. Plan Review - Documents Required
  4. Plan Review - On Hold-Incomplete
  5. Plan Review - On Hold-Incomplete
  6. Plan Review - Corrections Needed
  7. Plan Review - Corrections Needed
  8. Plan Review - Corrections Needed
  9. Plan Review - Corrections Needed
  10. Plan Review - Documents Required
  11. Plan Review - On Hold-Incomplete
  12. Plan Review - On Hold-Incomplete
  13. Zoning Review - Corrections Needed
  14. Plan Review - Corrections Needed
  15. Zoning Review - Corrections Needed
  16. Plan Review - Corrections Needed
  17. Zoning Review - Corrections Needed
  18. Plan Review - Corrections Needed
  19. Zoning Review - Corrections Needed
  20. Zoning Review - Corrections Needed
  21. Zoning Review - Documents Required
  22. Zoning Review - Documents Required
  23. Plan Review - Plumbing Approved
  24. Plan Review - Mechanical Approved
  25. Plan Review - Electrical Approved
  26. Plan Review - Building Approved
  27. Plan Review - Reviewed
  28. Zoning Review - Reviewed
  29. Final Review - Processing
  30. Final Review - Reviewed
  31. Final Review - Payment Needed
  32. Final Review - Payment Needed
  33. Final Review - Payment Needed
  34. Final Review - Payment Needed
  35. Final Review - Payment Needed
  36. Final Review - Payment Needed
  37. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Oct 5, 2023

    Septic Release Inspection

    Inspected by Health Dept