Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Anthony Aslan |
12/15/2023 |
Passed: Engineering - Setbacks |
Tight Lot May Need Surveyor Verification |
Anthony Aslan |
12/15/2023 |
Passed: Electrical - Temporary Service |
|
Anthony Aslan |
12/15/2023 |
Release to power company |
|
Anthony Aslan |
12/15/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
1/19/2024 |
Passed: Building - Slab |
|
Anthony Aslan |
2/7/2024 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Hanger |
Anthony Aslan |
2/29/2024 |
Failed: Building - Slab |
Not Ready |
Anthony Aslan |
3/8/2024 |
Cancelled: Building - Slab |
|
Neonta Anderson |
3/15/2024 |
Passed: Building - Slab |
|
Troy Crews |
3/19/2024 |
Passed: Building - Roof Decking |
Residence Only Hanger Pending |
Matt Forsyth |
4/30/2024 |
Passed: Building - Wall Sheathing |
Residence Only Hanger Pending |
Matt Forsyth |
4/30/2024 |
Passed: Building - Roof Decking |
Hanger |
Anthony Aslan |
5/16/2024 |
Passed: Building - Wall Sheathing |
Hanger |
Anthony Aslan |
5/16/2024 |
Passed: Building - Framing |
|
Anthony Aslan |
5/21/2024 |
Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
6/11/2024 |
Passed: Mechanical - Rough In |
|
Gary Pitzer |
6/11/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
No Tubs Or Showers Set |
Gary Pitzer |
6/11/2024 |
Passed: Building - Insulation |
House And Hanger |
Anthony Aslan |
6/18/2024 |
Passed: Electrical - Permanent Power |
Need Septic Release |
Anthony Aslan |
10/24/2024 |
Release to power company |
|
Melissa Garber |
11/8/2024 |
Septic Release Inspection |
|
Health Dept |
11/8/2024 |
Certificate-Release Certificate |
|
Gary Pitzer |
12/12/2024 |
Passed: Building - Final |
Cannot Closed Permit Or Release Certificate Of Occupancy Due To Missing Required Documents. |
Gary Pitzer |
12/12/2024 |