| Application #: | 63230 |
| Permit #: |
000048757 |
| Related Permit: |
|
| Submitted: | Wednesday, November 1, 2023 |
| Issued: | Thursday, November 30, 2023 |
| Expires: | Monday, April 15, 2024 |
| Completed: | Monday, April 15, 2024 |
| Status: |
Completed |
| Septic Release? |
Yes |
Notes
NON- HABITABLE STRUCTURE
| Elevation regulation |
Accessory Use |
| Finished floor requirement |
Non-Habitable Structure |
| Fema map number |
12023C0280D |
| In floodway |
N |
| Type of Structure |
Garage |
| Commercial or Residential? |
Residential |
| Total Area (Sqft) |
700 |
| Septic# (00-0000) or (X00-000) |
23-0733 |
| Setbacks Front |
30' |
| Setback Side 1 |
25' |
| Setback Side 2 |
25' |
| Setback Rear |
200' |
| Building Code Construction Type |
III |
| Building Code Element |
B |
| Building Code Occupancy Types |
Storage |
| Occupancy Use Title |
NON-HABITABLE structure |
| Dev Permit # |
F023- |
| Building Code Edition |
2023 Florida Building Code 8th Edition and 2020 National Electrical Code |
| Building Height |
17' |
| Building Length |
28' |
| Building Width |
28' |
| Service Amps |
20 |
| 11/1/2023 |
Application pending. |
| 11/1/2023 |
Application submitted by applicant. |
| 11/6/2023 |
Point Review - On Hold-Incomplete |
| 11/16/2023 |
Point Review - On Hold-Incomplete |
| 11/20/2023 |
Point Review - Printed-Online Application |
| 11/20/2023 |
Plan Review - Documents Required |
| 11/21/2023 |
Plan Review - Reviewed |
| 11/27/2023 |
Zoning Review - Reviewed |
| 11/30/2023 |
Final Review - Reviewed |
| 11/30/2023 |
Final Review - Payment Needed |
| 11/30/2023 |
Permit Issued |
| Name / Business |
License |
Title |
Role |
Isaiah Cully Ic Construction Llc
|
CBC1259655 |
Building Contractor |
Contractor |
Everton D Ruddock D&s Lighting Inc
|
EC13003800 |
Electrical Contractor |
Subcontractor |
| Inspection |
Notes |
Performed By |
Date |
| Septic Release Inspection |
|
Health Dept |
11/7/2023 |
| Passed: Building - Footer |
|
Matt Forsyth |
12/21/2023 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
12/21/2023 |
| Passed: Building - Slab |
The Perimeter Bar Always Needs To Be Tied Up Three Quarter Clearance Plastic Cut Back Away From Block |
Matt Forsyth |
1/18/2024 |
| Passed: Building - Framing |
|
Troy Crews |
2/16/2024 |
| Passed: Building - Roof Decking |
|
Troy Crews |
2/16/2024 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
2/16/2024 |
| Passed: Engineering - Access Road/Driveway Right-of-Way Integrity Inspection |
|
Matt Forsyth |
4/15/2024 |
| Passed: Building - Final |
|
Matt Forsyth |
4/15/2024 |