New Residential Construction
Permit
| Application #: | 63046 |
| Permit #: |
000048755 |
| Related Permit: |
|
| Submitted: | Wednesday, October 18, 2023 |
| Issued: | Thursday, November 30, 2023 |
| Expires: | Tuesday, August 13, 2024 |
| Completed: | Tuesday, August 13, 2024 |
| Status: |
Completed |
| Septic Release? |
Yes |
Notes
MFE= 1' ABOVE THE ROAD
Job Details
| Elevation regulation |
Minimum Requirement |
| Finished floor requirement |
One foot above the road |
| Fema map number |
12023C0420C |
| In floodway |
N |
| This is the construction of a |
Single Family Dwelling |
| Setbacks Front |
30' |
| Setback Side 1 |
25' |
| Setback Side 2 |
25' |
| Setbacks Rear |
25' |
| Stories |
1 |
| Heated Area (Sqft) |
3116 |
| Total Area (Sqft) |
3316 |
| Building Height |
17 |
| Building Code Construction Type |
V |
| Building Code Element |
B |
| Building Code Occupancy Types |
Residential |
| Occupancy Use Title |
single family dwelling |
| Building Code Edition |
2023 Florida Building Code 8th Edition and 2020 National Electrical Code |
| Septic# (00-0000) or (X00-000) |
23-0743 |
| Sealed roof decking options. (Must select one option per FBC 2023 8th Edition) |
Other (explain) |
| Sealed roof decking explanation for other option. |
part of building |
| Service Amps |
200 |
Review Notes
| 10/18/2023 |
Application pending. |
| 10/18/2023 |
Application submitted by applicant. |
| 10/19/2023 |
Point Review - Printed-Online Application |
| 10/19/2023 |
Point Review - Reviewed |
| 10/30/2023 |
Plan Review - Corrections Needed |
| 11/3/2023 |
Plan Review - Documents Required |
| 11/6/2023 |
Plan Review - Building Approved |
| 11/6/2023 |
Plan Review - Electrical Approved |
| 11/6/2023 |
Plan Review - Mechanical Approved |
| 11/6/2023 |
Plan Review - Plumbing Approved |
| 11/6/2023 |
Plan Review - Fuel/Gas Approved |
| 11/6/2023 |
Plan Review - Reviewed |
| 11/16/2023 |
Zoning Review - Reviewed |
| 11/16/2023 |
Final Review - Reviewed |
| 11/16/2023 |
Final Review - Payment Needed |
| 11/20/2023 |
Final Review - Payment Needed |
| 11/22/2023 |
Final Review - Payment Needed |
| 11/30/2023 |
Permit Issued |
Contractors
| Name / Business |
License |
Title |
Role |
Kevin L Bedenbaugh Jr Plumb Level Construction Co Llc
|
CGC1516042 |
General Contractor |
Contractor |
Kevin L Bedenbaugh Jr Plumb Level Construction Co Llc
|
CCC1329482 |
Roofing Contractor |
Subcontractor |
Cody Barrs Barrs Plumbing Inc
|
CFC1427145 |
Plumbing Contractor |
Subcontractor |
Ryan Felknor Felknor Electric, Inc.
Employees Workers Comp Expired. |
EC13003153 |
Electrical Contractor |
Subcontractor |
Clinton G Wilson Wilson Heat & Air Inc
|
CAC057886 |
Class B A/c |
Subcontractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Need Compaction On Slab Inspection |
Anthony Aslan |
12/6/2023 |
| Passed: Building - Monolithic Slab |
|
Anthony Aslan |
12/12/2023 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
12/12/2023 |
| Passed: Building - Framing |
Metal Building |
Anthony Aslan |
4/12/2024 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
4/12/2024 |
| Passed: Mechanical - Rough In |
|
Anthony Aslan |
4/12/2024 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
4/12/2024 |
| Passed: Building - Insulation |
|
Troy Crews |
4/18/2024 |
| Passed: Electrical - Temporary Service |
|
Anthony Aslan |
5/3/2024 |
| Release to power company |
|
Anthony Aslan |
5/3/2024 |
| Passed: Electrical - Permanent Power |
Need Septic Final |
Anthony Aslan |
7/10/2024 |
| Release to power company |
|
Melissa Garber |
7/19/2024 |
| Septic Release Inspection |
|
Health Dept |
7/19/2024 |
| Passed: Building - Final |
|
Anthony Aslan |
8/13/2024 |