Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
Need Elevation Letter At Slab |
Anthony Aslan |
11/6/2023 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
11/6/2023 |
Passed: Electrical - Temporary Service |
|
Anthony Aslan |
12/14/2023 |
Failed: Plumbing/Gas - 1st Underground Rough–In |
Piping No Pressure, And Must Be Filled With Water |
Anthony Aslan |
12/14/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
12/20/2023 |
Release to power company |
|
Anthony Aslan |
12/29/2023 |
Passed: Building - Slab |
|
Anthony Aslan |
1/3/2024 |
Septic Release Inspection |
|
Health Dept |
2/6/2024 |
Failed: Building - Framing |
Last Inspection Was Rough Plumbing
will Need Engineer To Certify Asbuilt Condition Of The House, Missing Slab Inspection And Nailing Inspections |
Anthony Aslan |
3/20/2024 |
Failed: Electrical - 1st Underground Rough–In |
Refer To Framing Notes |
Anthony Aslan |
3/20/2024 |
Failed: Mechanical - Rough In |
Refer To Framing Notes |
Anthony Aslan |
3/20/2024 |
Failed: Plumbing/Gas - 2nd Rough-In |
Refer To Framing Notes |
Anthony Aslan |
3/20/2024 |
Passed: Building - Roof Decking |
Engineer Letter Received |
Anthony Aslan |
4/2/2024 |
Passed: Building - Slab |
Engineer Letter Received |
Anthony Aslan |
4/2/2024 |
Passed: Building - Wall Sheathing |
Engineer Letter Received |
Anthony Aslan |
4/2/2024 |
Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
4/2/2024 |
Passed: Mechanical - Rough In |
Foam On Boots
exhaust Fan Venting
check At Insulation Inspection |
Anthony Aslan |
4/2/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
4/2/2024 |
Passed: Building - Framing |
Nails Straps Back Porch - H2.5 Mb
draft Block Bonus
check At Insulation Inspection |
Anthony Aslan |
4/2/2024 |
Passed: Building - Insulation |
Spray Foam All |
Anthony Aslan |
4/11/2024 |
Passed: Electrical - Permanent Power |
|
Anthony Aslan |
3/11/2025 |
Release to power company |
|
Anthony Aslan |
3/11/2025 |
Cancelled: Electrical - Utility Pole Final |
|
Anthony Aslan |
3/11/2025 |
Failed: Building - Final |
Blower Door Test
final Termite
no Locking Caps A/c Condenser, No Uv Insulation On A/c Piping, Need Pictures On Boots Sealed To Sheet Rock
back Flows On Hose Bibs
kitchen Sink Drain Not Installed
some Outlets Not Tripping Afci Breakers |
Anthony Aslan |
4/21/2025 |
Passed: Building - Final |
Need Better Copy Of Termite Final Prior To Co-- 5.1.25 Mg |
Anthony Aslan |
4/25/2025 |