Remodel
Permit
| Application #: | 61784 |
| Permit #: |
000048451 |
| Related Permit: |
|
| Submitted: | Thursday, July 6, 2023 |
| Issued: | Tuesday, August 26, 2025 |
| Expires: | Tuesday, September 2, 2025 |
| Completed: | Tuesday, September 2, 2025 |
| Status: |
Completed |
| Septic Release? |
Yes |
Job Details
| Finished floor requirement |
|
| Fema map number |
12023C0466C |
| Description of the work being performed: |
complete interior remodel |
| Commercial or Residential? |
Residential |
| Type of Structure |
House |
| Building Code Construction Type |
V |
| Building Code Element |
B |
| Building Code Occupancy Types |
Residential |
| Occupancy Use Title |
SINGLE FAMILY DWELLING |
| Septic# |
23-0280 |
| Dev Permit # |
F023- |
| Building Code Edition |
2020 Florida Building Code 7th Edition and 2017 National Electrical Code |
Review Notes
| 7/6/2023 |
Application Converted |
| 7/21/2023 |
Plan Review - Reviewed |
| 8/3/2023 |
Plan Review - Reviewed |
| 8/3/2023 |
Point Review - Reviewed |
| 8/8/2023 |
Zoning Review - Processing |
| 8/22/2023 |
Zoning Review - Documents Required |
| 9/20/2023 |
Zoning Review - Reviewed |
| 9/20/2023 |
Final Review - Processing |
| 9/28/2023 |
Final Review - Processing |
| 10/3/2023 |
Final Review - Documents Required |
| 10/19/2023 |
Final Review - Reviewed |
| 10/19/2023 |
Final Review - Payment Needed |
| 10/19/2023 |
Permit Issued |
| 7/9/2025 |
Final Review - Corrections Needed |
| 7/15/2025 |
Final Review - Corrections Needed |
| 8/26/2025 |
Permit Reissued |
Contractors
| Name / Business |
License |
Title |
Role |
Kip Maranto Kip Maranto Construction Inc
Liability Insurance & Workers Comp Expired. |
CBC1262465 |
Cert. Building |
Contractor |
Hal Maranto Maranto Refrigeration/hvac
Liability Insurance Expired. |
CAC1814240 |
Cert. Class B A/c |
Subcontractor |
Mark Dawson Paradise Plumbing Services, Llc.
|
CFC1427245 |
Plumbing Contractor |
Subcontractor |
Trever J Townsend Townsend Electrical Contractors, Llc
|
ER13016105 |
Reg. Electrical |
Subcontractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
3/26/2024 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
6/26/2024 |
| Passed: Building - Insulation |
|
Matt Forsyth |
7/2/2024 |
| Septic Release Inspection |
|
Health Dept |
7/10/2025 |
| Cancelled: Plumbing/Gas - Sanitary |
|
Matt Forsyth |
8/29/2025 |
| Cancelled: Plumbing/Gas - Water Pipe |
|
Matt Forsyth |
8/29/2025 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
8/29/2025 |
| Release to power company |
|
Matt Forsyth |
8/29/2025 |
| Rescheduled 9/2/2025:Building - Final |
|
Troy Crews |
9/2/2025 |
| Passed: Building - Final |
|
Matt Forsyth |
9/2/2025 |