Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Smith, Blake |
10/11/2023 |
Passed: Building - Footer |
Need Porta Potty On Site |
Matt Forsyth |
10/25/2023 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
10/25/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
11/22/2023 |
Failed: Building - Slab |
Work Needs To Be Finished Pour Ready |
Matt Forsyth |
11/30/2023 |
Passed: Building - Slab |
|
Matt Forsyth |
12/1/2023 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
12/18/2023 |
Release to power company |
|
Matt Forsyth |
12/18/2023 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
1/3/2024 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
1/3/2024 |
Failed: Building - Framing |
Two Headers Need Nailing Top And Bottom 12"oc |
Matt Forsyth |
3/5/2024 |
Failed: Electrical - 2nd Rough-In |
Need Two 20amp Receptacles In Two Car Garage |
Matt Forsyth |
3/5/2024 |
Failed: Mechanical - Rough In |
Need Nail Plate On Dryer Vent Stack |
Matt Forsyth |
3/5/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
3/5/2024 |
Passed: Building - Framing |
|
Matt Forsyth |
3/8/2024 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
3/8/2024 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
3/8/2024 |
Passed: Building - Insulation |
Walls Only |
Matt Forsyth |
3/14/2024 |
Passed: Electrical - Permanent Power |
Septic Needed |
Matt Forsyth |
4/24/2024 |
Passed: Engineering - Final Driveway |
Install Min, 32 ' × 18 " Corr Metal Culvert W / Concrete Mitred Ends, W / 6 " × 6 " Welded Wire, Rebar Or Culvert Bolts In Mitred Ends, Concrete Mitred Ends W - 4ft X L - 5ft, And With 4 Inches Of Limerock On Top Cover. |
Smith, Blake |
5/10/2024 |
Release to power company |
Rec'd Septic |
Matt Forsyth |
5/15/2024 |
Septic Release Inspection |
|
Health Dept |
5/15/2024 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
5/16/2024 |
Release to power company |
|
Matt Forsyth |
5/16/2024 |
Passed: Building - Final |
|
Troy Crews |
7/3/2024 |