Permit Details

Permit Search

Permit

New Residential Construction

362 NW EMPORIA GLN
LAKE CITY, FL 32055

Permit #
000048386
Application #
62257
Status Completed
  1. Submitted Aug 23, 2023
  2. Issued Oct 10, 2023
  3. Expires Jan 7, 2025
  4. Completed Jul 11, 2024

Property

Parcel #
02272-101
Owner
Urrutia Jose A, Urrutia Nitza M
Acres
5.52
Subdivision
Lakewood Estates
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0283D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
2
Heated Area (Sqft)
2784
Total Area (Sqft)
4151
Building Height
24
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
23-0655
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Point Review - Reviewed
  5. Plan Review - Building Approved
  6. Plan Review - Electrical Approved
  7. Plan Review - Mechanical Approved
  8. Plan Review - Plumbing Approved
  9. Plan Review - Fuel/Gas Approved
  10. Plan Review - Reviewed
  11. Zoning Review - Reviewed
  12. Plan Review - Reviewed
  13. Final Review - Documents Required
  14. Final Review - Reviewed
  15. Final Review - Payment Needed
  16. Permit Issued

Contractors

  • Isaiah Cully

    Ic Construction Llc

    License
    CBC1259655
    Title
    Building Contractor
    Role
    Contractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Tyler M Turner

    Tmt Roofing Llc

    License
    CCC1330410
    Title
    Cert Roofing
    Role
    Subcontractor
  • Everton D Ruddock

    D&s Lighting Inc

    License
    EC13003800
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor

Inspections

  1. Oct 11, 2023

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Oct 11, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Nov 3, 2023

    Electrical -1st Underground Rough–In

    Underslab

    Inspected by Gary Pitzer

  4. Nov 3, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Gary Pitzer

  5. Nov 3, 2023

    Passed: Building - Slab

    Plastic Taped Wire And Rebar

    Inspected by Gary Pitzer

  6. Dec 20, 2023

    Passed: Building - Roof Decking

    Inspected by Gary Pitzer

  7. Dec 20, 2023

    Passed: Building - Wall Sheathing

    Inspected by Gary Pitzer

  8. Jan 18, 2024

    Passed: Building - Framing

    Inspected by Gary Pitzer

  9. Jan 18, 2024

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Gary Pitzer

  10. Feb 16, 2024

    Plumbing/Gas-Tub Set/Shower Pan

    All Rough Piping Completed, Tub And Showers Flooded

    Inspected by Gary Pitzer

  11. Feb 16, 2024

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  12. Feb 16, 2024

    Passed: Mechanical - Rough In

    Inspected by Gary Pitzer

  13. Feb 29, 2024

    Passed: Building - Insulation

    Foam Roof,batts In Walls

    Inspected by Gary Pitzer

  14. Mar 28, 2024

    Passed: Electrical - Temporary Service

    Inspected by Gary Pitzer

  15. Mar 28, 2024

    Release to power company

    Inspected by Gary Pitzer

  16. Jul 5, 2024

    Passed: Electrical - Permanent Power

    Energized

    Inspected by Gary Pitzer

  17. Jul 5, 2024

    Release to power company

    Inspected by Gary Pitzer

  18. Jul 10, 2024

    Failed: Building - Final

    Smoke Detectors Not All Functioning Together

    Inspected by Gary Pitzer

  19. Jul 11, 2024

    Passed: Building - Final

    Inspected by Gary Pitzer