Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
|
Anthony Aslan |
10/24/2023 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
10/24/2023 |
Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
11/20/2023 |
Failed: Electrical - Temporary Service |
Pole Not Installed Laying On Ground |
Anthony Aslan |
11/20/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
11/20/2023 |
Passed: Building - Slab |
|
Troy Crews |
12/1/2023 |
Passed: Electrical - Temporary Service |
|
Anthony Aslan |
12/12/2023 |
Release to power company |
|
Anthony Aslan |
12/12/2023 |
Passed: Building - Framing |
Missing Straps On Uplift Marked, Check On Next Inspection |
Anthony Aslan |
1/10/2024 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Anthony Aslan |
1/10/2024 |
Cancelled: Building - Wall Sheathing |
|
Anthony Aslan |
1/10/2024 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
1/10/2024 |
Failed: Electrical - 2nd Rough-In |
No 20amp Circuit In Garage |
Anthony Aslan |
2/5/2024 |
Failed: Mechanical - Rough In |
No Screws In Kitchen Exhaust Piping, No Straps On Any Of Bath Fan Exhaust Venting |
Anthony Aslan |
2/5/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
2/5/2024 |
Passed: Electrical - 2nd Rough-In |
Corrections Made |
Anthony Aslan |
2/7/2024 |
Passed: Mechanical - Rough In |
Corrections Made |
Anthony Aslan |
2/7/2024 |
Passed: Building - Insulation |
Walls Only |
Anthony Aslan |
2/12/2024 |
Passed: Electrical - Permanent Power |
Need Septic Release |
Anthony Aslan |
5/6/2024 |
Release to power company |
Rec'd Septic |
Anthony Aslan |
5/14/2024 |
Septic Release Inspection |
|
Health Dept |
5/14/2024 |
Failed: Building - Final |
Need To Seal Up Block By A/c & Water Supply
need Kitchen Outlet Circuit Corrected, Tripping Breaker
no Light Bulb In Attic
need Blower Door
need Final Termite
need Grade To Be Away From House |
Anthony Aslan |
8/14/2024 |
Passed: Building - Final |
Corrections Made, Docs Uploaded |
Anthony Aslan |
8/19/2024 |