| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
10/3/2023 |
| Passed: Building - Footer |
|
Anthony Aslan |
10/9/2023 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
10/9/2023 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
10/30/2023 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
10/30/2023 |
| Passed: Building - Framing |
|
Anthony Aslan |
12/12/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
12/12/2023 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Anthony Aslan |
12/12/2023 |
| Passed: Electrical - Temporary Service |
|
Anthony Aslan |
12/12/2023 |
| Release to power company |
|
Anthony Aslan |
12/12/2023 |
| Failed: Mechanical - Rough In |
No Gaskets On Return Boots
fresh Air Not Insulated
no Straps On Exhaust Fan Piping |
Anthony Aslan |
12/13/2023 |
| Failed: Plumbing/Gas - 2nd Rough-In |
No Pressure On Piping |
Anthony Aslan |
12/13/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Pressure On System |
Anthony Aslan |
12/14/2023 |
| Passed: Mechanical - Rough In |
Corrections Made |
Anthony Aslan |
12/14/2023 |
| Passed: Building - Insulation |
Spray Foam Walls And Attic |
Anthony Aslan |
12/20/2023 |
| Passed: Electrical - Permanent Power |
Need Septic Final
outlets Off In Bedroom |
Anthony Aslan |
2/28/2024 |
| Release to power company |
|
Melissa Garber |
4/5/2024 |
| Septic Release Inspection |
|
Health Dept |
4/5/2024 |
| Passed: Building - Final |
|
Anthony Aslan |
4/23/2024 |