Permit Details

Permit Search

Permit

Additions

157 SE SHADY WAY
LULU, FL 32061

Permit #
000048255
Application #
57274
Status Permit Issued
  1. Submitted Feb 28, 2023
  2. Issued Sep 22, 2023
  3. Expires Dec 15, 2026
  4. Completed —

Property

Parcel #
10474-000
Owner
Parrish Chelsea E Croft,
Acres
1.92
Subdivision
Lulu
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Permit Issued
Septic release
Not yet released
Related permit
—

Job Details

Elevation regulation
Existing Building
Finished floor requirement
Meet existing structure
Fema map number
12023C0430C
In floodway
N
Description of addition:
2Bedrooms,1 bathroom
Select driveway access to property:
Private Drive
Fire sprinklers?
No
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setback Rear
25'
Stories
1
Heated Area (Sqft)
1800
Total Area (Sqft)
1800
Total Estimated Cost
60000
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Dev Permit #
F023-
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic#
23-0506
Is this an addition for commercial or residential use?
Residential
Sealed roof decking options. (Must select one.)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - On Hold-Incomplete
  4. Point Review - Email Sent
  5. Point Review - On Hold-Incomplete
  6. Point Review - On Hold-Incomplete
  7. Point Review - Printed-Online Application
  8. Point Review - Reviewed
  9. Plan Review - Documents Required
  10. Plan Review - On Hold-Incomplete
  11. Plan Review - On Hold-Incomplete
  12. Plan Review - On Hold-Incomplete
  13. Plan Review - Building Approved
  14. Plan Review - Electrical Approved
  15. Plan Review - Mechanical Approved
  16. Plan Review - Plumbing Approved
  17. Plan Review - Reviewed
  18. Plan Review - Documents Required
  19. Zoning Review - Reviewed
  20. Plan Review - Documents Required
  21. Final Review - Documents Required
  22. Plan Review - Documents Required
  23. Final Review - Documents Required
  24. Final Review - Documents Required
  25. Plan Review - Reviewed
  26. Final Review - Payment Needed
  27. Final Review - Payment Needed
  28. Final Review - Payment Needed
  29. Permit Issued

Contractors

This is an owner-builder project.

  1. Jan 22, 2024

    Passed: Building - Footer

    Inspected by Anthony Aslan

  2. Jan 22, 2024

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  3. Mar 15, 2024

    Passed: Building - Framing

    Partial, Need To Do Porch South End

    Inspected by Anthony Aslan

  4. Mar 15, 2024

    Passed: Building - Wall Sheathing

    South End Part Of House

    Inspected by Anthony Aslan

  5. May 2, 2024

    Passed: Building - Roof Decking

    All Roof Decking Complete

    Inspected by Anthony Aslan

  6. May 2, 2024

    Passed: Building - Framing

    Need Pictures Of Windows Installation

    Inspected by Anthony Aslan

  7. May 2, 2024

    Passed: Building - Wall Sheathing

    All Wall Sheathing Complete

    Inspected by Anthony Aslan

  8. Oct 15, 2024

    Passed: Building - Wall Sheathing

    Spot Check For Time

    Inspected by Anthony Aslan

  9. Apr 9, 2025

    Passed: Building - Wall Sheathing

    Partial

    Inspected by Troy Crews

  10. Oct 1, 2025

    Passed: Building - Spot Check

    Need To Get Rough-in Inspections Of All Trades need Energy Form, Total Gut Remodel

    Inspected by Anthony Aslan

  11. Dec 5, 2025

    Passed: Mechanical - Rough In

    Inspected by Christian Allen

  12. Dec 5, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Christian Allen

  13. Dec 5, 2025

    Failed: Plumbing/Gas - 2nd Rough-In

    No Drain Line Installed...or Gas Line

    Inspected by Christian Allen

  14. Dec 5, 2025

    Failed: Plumbing/Gas - Tub Set/Shower Pan

    Drain Line Not Complete For Shower

    Inspected by Christian Allen

  15. Dec 23, 2025

    Failed: Building - Insulation

    Need To Complete Plumbing And Gas Inspections Prior To Insulation

    Inspected by Troy Crews

  16. Dec 23, 2025

    Passed: Building - Insulation

    Inspected by Christian Allen

  17. Dec 23, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Christian Allen

  18. Jun 18, 2026

    Passed: Building - Window Attachment

    Inspected by Christian Allen