| 8/18/2022 |
Application pending. |
| 8/18/2022 |
City of Lake City |
| 8/31/2022 |
Point Review - On Hold-Incomplete |
| 9/15/2022 |
Point Review - On Hold-Incomplete |
| 10/21/2022 |
Point Review - On Hold-Incomplete |
| 11/23/2022 |
Point Review - On Hold-Incomplete |
| 12/9/2022 |
Point Review - Printed-Online Application |
| 12/9/2022 |
Point Review - Reviewed |
| 12/21/2022 |
Plan Review - Building Approved |
| 12/21/2022 |
Plan Review - Electrical Approved |
| 12/21/2022 |
Plan Review - Mechanical Approved |
| 12/21/2022 |
Plan Review - Plumbing Approved |
| 12/21/2022 |
Plan Review - Reviewed |
| 12/27/2022 |
Zoning Review - Reviewed |
| 12/27/2022 |
Final Review - Documents Required |
| 12/28/2022 |
Final Review - Documents Required |
| 12/29/2022 |
Final Review - Documents Required |
| 1/3/2023 |
Final Review - Documents Required |
| 1/5/2023 |
Final Review - Documents Required |
| 1/9/2023 |
Final Review - Documents Required |
| 2/6/2023 |
Final Review - Documents Required |
| 2/23/2023 |
Final Review - Documents Required |
| 3/13/2023 |
Final Review - Documents Required |
| 3/13/2023 |
Final Review - Documents Required |
| 3/29/2023 |
Final Review - Documents Required |
| 4/12/2023 |
Final Review - Documents Required |
| 4/12/2023 |
Final Review - Reviewed |
| 4/12/2023 |
Final Review - Payment Needed |
| 5/11/2023 |
Final Review - Payment Needed |
| 9/8/2023 |
Final Review - Contact the Building Dept |
| 9/15/2023 |
Final Review - Contact the Building Dept |
| 9/20/2023 |
Final Review - Payment Needed |
| 9/20/2023 |
Final Review - Contact the Building Dept |
| 9/20/2023 |
Permit Issued |