8/18/2023
|
Plan Review - Corrections Needed
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
|
8/18/2023
|
Plan Review - Building Approved
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
|
8/18/2023
|
Plan Review - Electrical Approved
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
|
8/18/2023
|
Plan Review - Mechanical Approved
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
|
8/18/2023
|
Plan Review - Plumbing Approved
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
|
8/18/2023
|
Plan Review - Fuel/Gas Approved
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
|
8/18/2023
|
Plan Review - Reviewed
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
|
8/22/2023
|
Zoning Review - Reviewed
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
* MFE= 1' ABOVE THE ROAD
|
8/22/2023
|
Point Review - Received-Hard Copy Application
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
* MFE= 1' ABOVE THE ROAD
|
8/22/2023
|
Point Review - Reviewed
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
* MFE= 1' ABOVE THE ROAD
|
9/8/2023
|
Final Review - Documents Required
NEEDED:
**ENERGY FORM NOT SEER2 COMPLIANT (NEED BY FINAL REVIEW)
* MFE= 1' ABOVE THE ROAD
|
9/8/2023
|
Final Review - Processing
NEEDED:
* MFE= 1' ABOVE THE ROAD
|
9/15/2023
|
Final Review - Reviewed
* MFE= 1' ABOVE THE ROAD
|
9/15/2023
|
Final Review - Payment Needed
* MFE= 1' ABOVE THE ROAD
|
9/18/2023
|
Permit Issued
Permit #000048167 created and approved.
|
12/20/2023
|
Final Review - Payment Needed
* MFE= 1' ABOVE THE ROAD
|