| 5/11/2023 |
Application pending. |
| 5/15/2023 |
Application submitted by applicant. |
| 5/18/2023 |
Point Review - Printed-Online Application |
| 5/18/2023 |
Point Review - Reviewed |
| 6/7/2023 |
Plan Review - Documents Required |
| 6/12/2023 |
Plan Review - On Hold-Incomplete |
| 6/20/2023 |
Plan Review - Building Approved |
| 6/20/2023 |
Plan Review - Electrical Approved |
| 6/20/2023 |
Plan Review - Mechanical Approved |
| 6/20/2023 |
Plan Review - Plumbing Approved |
| 6/20/2023 |
Plan Review - Fuel/Gas Approved |
| 6/20/2023 |
Plan Review - Reviewed |
| 6/20/2023 |
Zoning Review - Documents Required |
| 6/21/2023 |
Zoning Review - Documents Required |
| 6/27/2023 |
Zoning Review - Documents Required |
| 6/30/2023 |
Zoning Review - Documents Required |
| 7/3/2023 |
Zoning Review - Documents Required |
| 7/6/2023 |
Zoning Review - Documents Required |
| 7/10/2023 |
Zoning Review - Documents Required |
| 7/11/2023 |
Zoning Review - Documents Required |
| 7/14/2023 |
Zoning Review - Documents Required |
| 7/24/2023 |
Zoning Review - Documents Required |
| 7/26/2023 |
Zoning Review - Documents Required |
| 8/3/2023 |
Zoning Review - Documents Required |
| 8/21/2023 |
Zoning Review - Processing |
| 8/25/2023 |
Zoning Review - Corrections Needed |
| 8/28/2023 |
Zoning Review - Documents Required |
| 9/1/2023 |
Zoning Review - Documents Required |
| 9/1/2023 |
Zoning Review - Documents Required |
| 9/5/2023 |
Zoning Review - Reviewed |
| 9/5/2023 |
Final Review - Processing |
| 9/15/2023 |
Final Review - Payment Needed |
| 9/15/2023 |
Permit Issued |