| Application #: | 62162 |
| Permit #: |
000048086 |
| Related Permit: |
|
| Submitted: | Tuesday, August 8, 2023 |
| Issued: | Tuesday, September 12, 2023 |
| Expires: | Wednesday, March 20, 2024 |
| Completed: | Wednesday, March 20, 2024 |
| Status: |
Completed |
| Septic Release? |
Yes |
Notes
MFE 1' ABOVE THE ROAD
| Elevation regulation |
Minimum Requirement |
| Finished floor requirement |
One foot above the road |
| Fema map number |
12023C0370C |
| In floodway |
N |
| This is the construction of a |
Single Family Dwelling |
| Setbacks Front |
30' |
| Setback Side 1 |
25' |
| Setback Side 2 |
25' |
| Setbacks Rear |
25' |
| Stories |
1 |
| Heated Area (Sqft) |
2019 |
| Total Area (Sqft) |
2400 |
| Building Height |
20 |
| Building Code Construction Type |
V |
| Building Code Element |
B |
| Building Code Occupancy Types |
Residential |
| Occupancy Use Title |
single family dwelling |
| Building Code Edition |
2020 Florida Building Code 7th Edition and 2017 National Electrical Code |
| Septic# (00-0000) or (X00-000) |
23-0584 |
| Sealed roof decking options. (Must select one option per FBC 2023 8th Edition) |
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified. |
| Service Amps |
200 |
| 8/8/2023 |
Application pending. |
| 8/8/2023 |
Application submitted by applicant. |
| 8/16/2023 |
Point Review - Printed-Online Application |
| 8/16/2023 |
Point Review - Reviewed |
| 8/18/2023 |
Plan Review - Corrections Needed |
| 8/18/2023 |
Plan Review - Building Approved |
| 8/18/2023 |
Plan Review - Electrical Approved |
| 8/18/2023 |
Plan Review - Mechanical Approved |
| 8/18/2023 |
Plan Review - Plumbing Approved |
| 8/18/2023 |
Plan Review - Fuel/Gas Approved |
| 8/18/2023 |
Plan Review - Reviewed |
| 8/22/2023 |
Zoning Review - Reviewed |
| 9/12/2023 |
Final Review - Reviewed |
| 9/12/2023 |
Final Review - Payment Needed |
| 9/12/2023 |
Permit Issued |
| 2/5/2024 |
Final Review - Payment Needed |
| Name / Business |
License |
Title |
Role |
Tabitha M Sibel Rjh Construction
County License & State License Expired. |
CGC1515388 |
General Contractor |
Contractor |
Cody Barrs Barrs Plumbing Inc
|
CFC1427145 |
Plumbing Contractor |
Subcontractor |
Robert Lynch Third Day Electric Llc
County License & State License Expired. |
EC13001947 |
Cert. Electrical |
Subcontractor |
Timothy D Shatto Shatto Heating & Air, Inc.
|
CAC057875 |
A/c Class B |
Subcontractor |
Tabitha M Sibel Rjh Construction
County License & State License Expired. |
CCC1331967 |
Cert. Roofing |
Subcontractor |
| Inspection |
Notes |
Performed By |
Date |
| Passed: Building - Footer |
|
Matt Forsyth |
9/25/2023 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
9/25/2023 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
11/1/2023 |
| Passed: Building - Footer |
Monolithic Slab |
Matt Forsyth |
11/9/2023 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
11/9/2023 |
| Passed: Building - Slab |
Monolithic Slab |
Matt Forsyth |
11/9/2023 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
11/29/2023 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
11/29/2023 |
| Cancelled: Building - Roof Decking |
|
Matt Forsyth |
12/6/2023 |
| Passed: Building - Framing |
|
Matt Forsyth |
12/18/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
12/18/2023 |
| Passed: Mechanical - Rough In |
Keep Clearances On Your Duckboard To Framing Members |
Matt Forsyth |
12/18/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Shower Floor Inspection Needed And All Water And Tubs Tested |
Matt Forsyth |
12/18/2023 |
| Passed: Building - Insulation |
|
Matt Forsyth |
1/5/2024 |
| Passed: Electrical - Permanent Power |
Need Septic |
Matt Forsyth |
2/6/2024 |
| Release to power company |
Rec'd Septic |
Matt Forsyth |
2/21/2024 |
| Septic Release Inspection |
|
Health Dept |
2/21/2024 |
| Failed: Building - Final |
No Disconnect On Air Handler Electrical Panel Box Needs To Be Relabeled |
Matt Forsyth |
3/18/2024 |
| Passed: Building - Final |
|
Matt Forsyth |
3/20/2024 |