Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 485 SW JOE MARKHAM DR
LAKE CITY, FL 32024
Parcel #: 00469-105
Acres: 10.00
Owner: Tovar Argel Mancilla, Tovar Mercedes Del Carmen Mancilla
Subdivision: Shirley Gorospe Tract (division Of Land)
Zoning: ESA-2
Flood Zone: X
District: 2
Application #: 62162
Permit #: 000048086
Related Permit: Culvert Waiver: 000048085
Submitted: Tuesday, August 8, 2023
Issued: Tuesday, September 12, 2023
Expires: Wednesday, March 20, 2024
Completed: Wednesday, March 20, 2024
Status: Completed
Septic Release? Yes
Notes:
MFE 1' ABOVE THE ROAD
Job Details
Elevation regulation Minimum Requirement
Finished floor requirement One foot above the road
Fema map number 12023C0370C
In floodway N
This is the construction of a Single Family Dwelling
Setbacks Front 30'
Setback Side 1 25'
Setback Side 2 25'
Setbacks Rear 25'
Stories 1
Heated Area (Sqft) 2019
Total Area (Sqft) 2400
Building Height 20
Building Code Construction Type V
Building Code Element B
Building Code Occupancy Types Residential
Occupancy Use Title single family dwelling
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000) 23-0584
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition) two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps 200
Review Notes
8/8/2023 Application pending.
8/8/2023 Application submitted by applicant.
8/16/2023 Point Review - Printed-Online Application
8/16/2023 Point Review - Reviewed
8/18/2023 Plan Review - Corrections Needed
8/18/2023 Plan Review - Building Approved
8/18/2023 Plan Review - Electrical Approved
8/18/2023 Plan Review - Mechanical Approved
8/18/2023 Plan Review - Plumbing Approved
8/18/2023 Plan Review - Fuel/Gas Approved
8/18/2023 Plan Review - Reviewed
8/22/2023 Zoning Review - Reviewed
9/12/2023 Final Review - Reviewed
9/12/2023 Final Review - Payment Needed
9/12/2023 Permit Issued
2/5/2024 Final Review - Payment Needed
Contractors
Name/ Business License Title Role
Tabitha M Sibel
Rjh Construction
CGC1515388 General Contractor Contractor
Cody Barrs
Barrs Plumbing Inc
CFC1427145 Plumbing Contractor Subcontractor
Robert Lynch
Third Day Electric Llc
EC13001947 Cert. Electrical Subcontractor
Timothy D Shatto
Shatto Heating & Air, Inc.
CAC057875 A/c Class B Subcontractor
Tabitha M Sibel
Rjh Construction
CCC1331967 Cert. Roofing Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer Matt Forsyth 9/25/2023
Passed: Engineering - Setbacks Matt Forsyth 9/25/2023
Passed: Plumbing/Gas - 1st Underground Rough–In Matt Forsyth 11/1/2023
Passed: Building - Footer Monolithic Slab Matt Forsyth 11/9/2023
Passed: Engineering - Setbacks Matt Forsyth 11/9/2023
Passed: Building - Slab Monolithic Slab Matt Forsyth 11/9/2023
Passed: Building - Ext Strapping/Wall Sheathing Matt Forsyth 11/29/2023
Passed: Building - Roof Decking Matt Forsyth 11/29/2023
Cancelled: Building - Roof Decking Matt Forsyth 12/6/2023
Passed: Building - Framing Matt Forsyth 12/18/2023
Passed: Electrical - 2nd Rough-In Matt Forsyth 12/18/2023
Passed: Mechanical - Rough In Keep Clearances On Your Duckboard To Framing Members Matt Forsyth 12/18/2023
Passed: Plumbing/Gas - 2nd Rough-In Shower Floor Inspection Needed And All Water And Tubs Tested Matt Forsyth 12/18/2023
Passed: Building - Insulation Matt Forsyth 1/5/2024
Passed: Electrical - Permanent Power Need Septic Matt Forsyth 2/6/2024
Release to power company Rec'd Septic Matt Forsyth 2/21/2024
Septic Release Inspection Health Dept 2/21/2024
Failed: Building - Final No Disconnect On Air Handler Electrical Panel Box Needs To Be Relabeled Matt Forsyth 3/18/2024
Passed: Building - Final Matt Forsyth 3/20/2024
Documents
File Name Date File Size