Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Electric Conduit Installed 4 Island 623 0168 Matt |
Matt Forsyth |
10/23/2023 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
10/31/2023 |
Passed: Engineering - Setbacks |
|
Troy Crews |
10/31/2023 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
11/7/2023 |
Passed: Engineering - Setbacks |
|
Troy Crews |
11/7/2023 |
Passed: Building - Framing |
Exterior Metal Building Framing Complete |
Matt Forsyth |
2/2/2024 |
Cancelled: Electrical - Permanent Power |
|
Melissa Garber |
1/31/2025 |
Passed: Electrical - 1st Underground Rough–In |
Service Entrance Has Been Built |
Matt Forsyth |
2/3/2025 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
2/26/2025 |
Release to power company |
|
Matt Forsyth |
2/26/2025 |
Passed: Building - Framing |
|
Matt Forsyth |
5/8/2025 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
5/8/2025 |
Passed: Mechanical - Rough In |
Interior Exhaust Fan Duct Missing |
Matt Forsyth |
5/8/2025 |
Passed: Plumbing/Gas - 2nd Rough-In |
Nail Plates Missing On Vent Stack And Water Lines |
Matt Forsyth |
5/8/2025 |
Passed: Building - Insulation |
Batts. Wall And Ceiling |
Matt Forsyth |
5/13/2025 |
Passed: Electrical - Permanent Power |
Inspection Was From Meter Can Tobacco Dwelling 400 Meter Disconnect Too Many Garden Tools To Open Up The Service Panel No Branch Circuits In The Dwelling Have Been Run Yet Need Septic Release |
Matt Forsyth |
6/17/2025 |
Passed: Electrical - Permanent Power |
Service Panel Inside Looks Good Will Need To Be Relabeled For Final Inspection-- Final Septic Release Required Prior To Release Of Power-- 6.19.25 Mg |
Matt Forsyth |
6/18/2025 |
Release to power company |
|
Melissa Garber |
7/1/2025 |
Septic Release Inspection |
|
Health Dept |
7/1/2025 |
Submitted Power Release through FPL Portal |
|
Garber, Melissa |
7/1/2025 |