Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Plumbing Drains, Vents, Cross Over Water To Island, No Gas |
Gary Pitzer |
9/14/2023 |
Electrical -1st Underground Rough–In |
Steel Bonding |
Gary Pitzer |
9/18/2023 |
Passed: Building - Monolithic Slab |
|
Gary Pitzer |
9/18/2023 |
Passed: Engineering - Setbacks |
|
Gary Pitzer |
9/18/2023 |
Passed: Building - Vertical Cells/Columns |
|
Gary Pitzer |
10/2/2023 |
Passed: Building - Masonry Wall Reinforcing |
|
Gary Pitzer |
10/2/2023 |
Passed: Building - Lintel/Tie Beam |
|
Gary Pitzer |
10/2/2023 |
Cancelled: Building - Framing |
|
Bnztemp |
10/10/2023 |
Cancelled: Building - Masonry Wall Reinforcing |
|
Bnztemp |
10/10/2023 |
Cancelled: Building - Roof Decking |
|
Bnztemp |
10/10/2023 |
Cancelled: Building - Vertical Cells/Columns |
|
Bnztemp |
10/10/2023 |
Passed: Building - Framing |
Roof Framing, Anchor Straps And Bracing, Exterior Wall Furring |
Gary Pitzer |
10/16/2023 |
Passed: Building - Roof Decking |
|
Gary Pitzer |
10/16/2023 |
Passed: Building - Vertical Cells/Columns |
|
Gary Pitzer |
10/16/2023 |
Passed: Building - Framing |
|
Gary Pitzer |
10/30/2023 |
Passed: Building - Roof Decking |
|
Gary Pitzer |
10/30/2023 |
Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
10/30/2023 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Gary Pitzer |
10/30/2023 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Gary Pitzer |
10/30/2023 |
Failed: Building - Insulation |
Non Installed |
Gary Pitzer |
10/30/2023 |
Passed: Building - Insulation |
Eng Letter On File |
Gary Pitzer |
11/8/2023 |
Passed: Building - Lath/Stucco |
|
Gary Pitzer |
11/22/2023 |
Passed: Electrical - Permanent Power |
|
Gary Pitzer |
11/22/2023 |
Release to power company |
|
Gary Pitzer |
11/22/2023 |
Septic Release Inspection |
|
Health Dept |
12/14/2023 |
Cancelled: Building - Insulation |
|
Anthony Aslan |
12/28/2023 |
Cancelled: Building - Final |
|
Anthony Aslan |
12/28/2023 |
Passed: Building - Final |
|
Gary Pitzer |
1/3/2024 |