Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 207 SW HIGH FIELD TER
LAKE CITY, FL 32024
Parcel #: 03761-130
Acres: 4.99
Owner: Carroll Melinda S,
Subdivision: Meadowlands Phase 3
Zoning: A-3
Flood Zone: X
District: 4
Application #: 61404
Permit #: 000048018
Related Permit: Culvert: 000042615
Submitted: Friday, June 2, 2023
Issued: Friday, September 1, 2023
Expires: Friday, September 1, 2023
Completed: Friday, September 1, 2023
Status: Completed
Septic Release? Yes
Notes:
AFTER THE FACT PERMIT BASED ON ENGINEER LETTER, AND LICENSED SUB. CONTRACTORS
Job Details
This is the construction of a Single Family Dwelling
Heated Area (Sqft) 720
Total Area (Sqft) 720
Stories 1
Septic# (00-0000) or (X00-000) 22-0603
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Elevation regulation Subdivision Plat
Finished floor requirement 89
Document receieved No
Fema map number 12023C0485C
Review Notes
6/5/2023 Point Review - On Hold-Incomplete NEEDED: *SUB FORM SIGNATURES-- DUE TO LETTERS NOT BEING SIGNED *ENGINEER LETTER MUST STATE THAT BUILDING ACCEPTABLE AS IS FOR HABITABLE STRUCTURE-- CURRENT LETTER IS FOR FOUNDATION ONLY *ENV HEALTH SIGNED SITE PLAN APPROVAL *BLOWER DOOR TEST *ENGINEER ELEVATION LETTER
6/5/2023 Final Review - Documents Required NEEDED: *SUB FORM SIGNATURES-- DUE TO LETTERS NOT BEING SIGNED *ENGINEER LETTER MUST STATE THAT BUILDING ACCEPTABLE AS IS FOR HABITABLE STRUCTURE-- CURRENT LETTER IS FOR FOUNDATION ONLY *ENV HEALTH SIGNED SITE PLAN APPROVAL *BLOWER DOOR TEST *ENGINEER ELEVATION LETTER
6/5/2023 Final Review - On Hold-Incomplete NEEDED: *SUB FORM SIGNATURES-- DUE TO LETTERS NOT BEING SIGNED *ENGINEER LETTER MUST STATE THAT BUILDING ACCEPTABLE AS IS FOR HABITABLE STRUCTURE-- CURRENT LETTER IS FOR FOUNDATION ONLY *ENV HEALTH SIGNED SITE PLAN APPROVAL *BLOWER DOOR TEST *ENGINEER ELEVATION LETTER
6/27/2023 Plan Review - Documents Required NEEDED: *SUB FORM SIGNATURES-- DUE TO LETTERS NOT BEING SIGNED *ENGINEER LETTER MUST STATE THAT BUILDING ACCEPTABLE AS IS FOR HABITABLE STRUCTURE-- CURRENT LETTER IS FOR FOUNDATION ONLY *ENV HEALTH SIGNED SITE PLAN APPROVAL *BLOWER DOOR TEST *ENGINEER ELEVATION LETTER
6/29/2023 Final Review - On Hold-Incomplete NEEDED: *SUB FORM SIGNATURES-- DUE TO LETTERS NOT BEING SIGNED *ENGINEER LETTER MUST STATE THAT BUILDING ACCEPTABLE AS IS FOR HABITABLE STRUCTURE-- CURRENT LETTER IS FOR FOUNDATION ONLY *ENGINEER ELEVATION LETTER
6/30/2023 Plan Review - Documents Required NEEDED: *SUB FORM SIGNATURES-- DUE TO LETTERS NOT BEING SIGNED *ENGINEER LETTER MUST STATE THAT BUILDING ACCEPTABLE AS IS FOR HABITABLE STRUCTURE-- CURRENT LETTER IS FOR FOUNDATION ONLY *ENGINEER ELEVATION LETTER
7/3/2023 Plan Review - Documents Required NEEDED: *SUB FORM SIGNATURES-- DUE TO LETTERS NOT BEING SIGNED *ENGINEER LETTER MUST STATE THAT BUILDING ACCEPTABLE AS IS FOR HABITABLE STRUCTURE-- CURRENT LETTER IS FOR FOUNDATION ONLY *ENGINEER ELEVATION LETTER
7/6/2023 Plan Review - Documents Required NEEDED: *SUB FORM SIGNATURES-- DUE TO LETTERS NOT BEING SIGNED *ENGINEER LETTER MUST STATE THAT BUILDING ACCEPTABLE AS IS FOR HABITABLE STRUCTURE-- CURRENT LETTER IS FOR FOUNDATION ONLY *ENGINEER ELEVATION LETTER
7/14/2023 Plan Review - Documents Required NEEDED: *SUB FORM SIGNATURES-- DUE TO LETTERS NOT BEING SIGNED *ENGINEER LETTER MUST STATE THAT BUILDING ACCEPTABLE AS IS FOR HABITABLE STRUCTURE-- CURRENT LETTER IS FOR FOUNDATION ONLY *ENGINEER ELEVATION LETTER
7/24/2023 Plan Review - Plumbing Approved NEEDED: *ENGINEER ELEVATION LETTER PLAT CALLS FOR 89 ELEVATION EXISING GRADE IS LOWER
7/24/2023 Plan Review - Mechanical Approved NEEDED: *ENGINEER ELEVATION LETTER PLAT CALLS FOR 89 ELEVATION EXISING GRADE IS LOWER
7/24/2023 Plan Review - Electrical Approved NEEDED: *ENGINEER ELEVATION LETTER PLAT CALLS FOR 89 ELEVATION EXISING GRADE IS LOWER
7/24/2023 Plan Review - Building Approved NEEDED: *ENGINEER ELEVATION LETTER PLAT CALLS FOR 89 ELEVATION EXISING GRADE IS LOWER
7/24/2023 Plan Review - Reviewed NEEDED: *ENGINEER ELEVATION LETTER PLAT CALLS FOR 89 ELEVATION EXISING GRADE IS LOWER
7/24/2023 Zoning Review - Documents Required NEEDED: *ENGINEER ELEVATION LETTER NEEDED, PLAT CALLS FOR 89 ELEVATION EXISING GRADE IS LOWER
7/26/2023 Final Review - Documents Required NEEDED: *ENGINEER ELEVATION LETTER NEEDED, PLAT CALLS FOR 89 ELEVATION EXISING GRADE IS LOWER
8/25/2023 Final Review - Documents Required NEEDED: * ENGINEER ELEVATION LETTER NEEDED, PLAT CALLS FOR 89 ELEVATION EXISING GRADE IS LOWER
9/1/2023 Zoning Review - Reviewed
9/1/2023 Final Review - Reviewed
9/1/2023 Final Review - Payment Needed
9/1/2023 Permit Issued Permit #000048018 created and approved.
Contractors

This is an owner builder project.

Name/ Business License Title Role
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway Mccormick, David 8/24/2021
Septic Release Inspection Health Dept 6/16/2023
Certificate-Release Certificate Affidavit Basis Final C.o. Troy Crews 9/1/2023
Passed: Building - Final Approved On Affidavit Basis From Engineer And Licensed Sub Contractors. Noc Not Required As Work Has Been Completed For Some Time Troy Crews 9/1/2023