| Inspection |
Notes |
Performed By |
Date |
| Passed: Fire - Plan Review |
|
Shane Overstreet |
8/1/2023 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Water Will Be In Walls |
Troy Crews |
10/5/2023 |
| Passed: Plumbing/Gas - Water Pipe |
Water Lines In Slab |
Troy Crews |
10/11/2023 |
| Cancelled: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
10/12/2023 |
| Passed: Building - Footer |
|
Troy Crews |
10/18/2023 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
10/18/2023 |
| Passed: Building - Slab |
|
Troy Crews |
10/18/2023 |
| Passed: Building - Insulation |
|
Troy Crews |
12/12/2023 |
| Passed: Building - Framing |
|
Troy Crews |
12/12/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
12/12/2023 |
| Passed: Mechanical - Rough In |
Partial Hard Ceiling Areas |
Troy Crews |
12/12/2023 |
| Passed: Plumbing/Gas - Sanitary |
|
Troy Crews |
12/12/2023 |
| Passed: Plumbing/Gas - Water Pipe |
|
Troy Crews |
12/12/2023 |
| Rescheduled 1/5/2024:Electrical - Permanent Power |
|
Troy Crews |
1/3/2024 |
| Passed: Electrical - Permanent Power |
Need Septic Final |
Troy Crews |
1/5/2024 |
| Release to power company |
Verbal From E.h. On Septic For Release |
Troy Crews |
1/9/2024 |
| Release to power company |
Re-release Pwr Company Stated They Did Not Get Original Release |
Troy Crews |
1/11/2024 |
| Release to power company |
Re Release Adding Well |
Melissa Garber |
1/12/2024 |
| Septic Release Inspection |
|
Health Dept |
1/19/2024 |
| Passed: Building - Final |
Need Fire Final For Co |
Troy Crews |
2/5/2024 |
| Rescheduled 2/6/2024:Fire - Fire Final |
|
Troy Crews |
2/6/2024 |
| Rescheduled 2/9/2024:Fire - Fire Final |
|
Troy Crews |
2/9/2024 |
| Certificate-Release Certificate |
Rec'd Fire Final |
Troy Crews |
2/12/2024 |
| Passed: Fire - Fire Final |
|
Cpt.shane Overstreet |
2/12/2024 |
| (Requested) Fire-Fire Final |
|
|
|