Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Commercial Construction Permit
Address 702 NE OKINAWA ST
LAKE CITY, FL 32055
Parcel #: 07253-000
Acres: 34.69
Owner: Robbins Real Estate Inc
Subdivision:
Zoning: I
Flood Zone: X
District: 1
Application #: 61759
Permit #: 000047919
Related Permit:
Submitted: Monday, July 3, 2023
Issued: Friday, August 18, 2023
Expires: Wednesday, January 24, 2024
Completed: Wednesday, January 24, 2024
Status: Completed
Septic Release? Yes
Notes:
SDP2305
LAKE CITY UTLITY CUSTOMER SERVICE NOTES The City of Lake City provides natural gas to this location. Locates must be obtained to ensure that the existing utility infrastructure is not damaged or obstructed.
Job Details
This is the construction of a: kiln treatment plant
Setbacks Front 20'
Setback Side 1 15'
Setback Side 2 15'
Setback Rear 15'
Septic# (00-0000) or (X00-000) x23-113
Dev Permit # F023-
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Fema map number 12023C0305D
Review Notes
7/3/2023 City of Lake City Notified of Application within Utility Service Areas LC_GAS,.
7/5/2023 Point Review - Documents Required NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN E- SEAL PLANS NEED TO BE UPLOADED
7/5/2023 Point Review - Received-Hard Copy Application NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN E- SEAL PLANS NEED TO BE UPLOADED
7/5/2023 Point Review - Reviewed NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN E- SEAL PLANS NEED TO BE UPLOADED
7/5/2023 Plan Review - Documents Required NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN E- SEAL PLANS NEED TO BE UPLOADED
7/6/2023 Plan Review - Electrical Approved NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN
7/6/2023 Plan Review - Building Approved NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN
7/6/2023 Plan Review - Reviewed NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN
7/6/2023 Zoning Review - Reviewed NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN
7/6/2023 Final Review - Documents Required NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN
7/10/2023 Final Review - Documents Required NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN
7/12/2023 Final Review - Documents Required NEEDED * ESTIMATED COST OF CONSTRUCTION * ENVIRONMENTAL HEALTH SIGNED SITE PLAN
7/25/2023 Final Review - Documents Required NEEDED * ENVIRONMENTAL HEALTH SIGNED SITE PLAN
8/15/2023 Final Review - Payment Needed
8/18/2023 Permit Issued Permit #000047919 created and approved.
Contractors
Name/ Business License Title Role
James F Boone
C.a. Boone Construction Inc
County License & State License & Liability Insurance & Workers Comp Expired.
CGC1531762 Cert. General Contractor
Blake W Graham
Graham & Sons Electric Inc
EC13006720 Cert. Electrical Subcontractor
Inspections
Inspection Notes Performed By Date
Septic Release Inspection Health Dept 8/9/2023
Passed: Building - Ext Strapping/Wall Sheathing Troy Crews 12/6/2023
Passed: Building - Insulation Troy Crews 12/6/2023
Passed: Building - Roof Decking Welding Not Complete Troy Crews 12/6/2023
Passed: Electrical - Permanent Power Troy Crews 1/24/2024
Release to power company Troy Crews 1/24/2024
Passed: Building - Final Troy Crews 1/24/2024
Passed: Building - Roof Decking Troy Crews 1/24/2024