Search pages and services on the county website.
Choose the colors you prefer.
Permit
211 NE MCCLOSKEY AVELAKE CITY, FL 32055
Gregory F Kitchens
Siemens Industry Inc
County License & State License Expired.
David R Hardin
Stellar Industrial Solutions, Inc
Michael R Santarone
Stellar Contraction, Inc
County License & State License & Employees Workers Comp Expired.
Justin R Mcneely
Todd S Morgan
Comprehensive Energy Services Inc
County License & State License & Liability Insurance & Workers Comp Expired.
Passed: Fire - Plan Review
Inspected by Shane Overstreet
Passed: Building - Footer
All Interiors Except For East Row
Inspected by Troy Crews
Passed: Engineering - Setbacks
5 Pier Footers East Side
Ne 1/3 Of Permiter Foundation
Peer Foundations At Existing Building
Patrial East Side Perimiter And Partial North At Exiting Building Piers.
Remainder Of East Side Perimiter With Pads, And North Pads At Existing Building.
Piers At North Wall
3 Interiors South End Wall South End
Perimiter At Se Corner
Remainder Of Perimeter Footing South End
Passed: Electrical - 1st Underground Rough–In
North Side Parking Lot Conduits., Partial South Side.
Parking Lot Rough In
Passed: Building - Fire Rated Wall
Tilt Wall Panels For South End
Passed: Building - Slab
Stair Landings East Side Of Building
Stem Wall Pour East Side 3 Spots
Passed: Electrical - 2nd Rough-In
4 Bases 10 Ft Deep With Cage
Light Bases
Ligh Base Conduits.
Sections Of Parking Lot
Anchor Plates Bottom Of Tilt Wall Anchors Being Installed To Footer
Passed: Plumbing/Gas - 1st Underground Rough–In
Drains For Fire Room And And Drain For Existing Compressor Room.
Passed: Building - Masonry Wall Reinforcing
Sump Pit Footer
Drains For Commpresors
Passed: Building - Monolithic Slab
Compressor Room Slab
Last Parking Lot And Slab For Railroad Car
Loading Dock Stairs, Walls
1 St Tie In From Parking Lot Toward Builing, Inside Slab E- Mail Pictures
Passed: Electrical - Permanent Power
Inspected by Cpt.shane Overstreet
Front Break Area
Passed: Plumbing/Gas - Sanitary
Gang Bath Area
First Two Sections Of 10 Inch Slab
Passed: Building - Insulation
Gang Bath Hot Water Lines
Passed: Plumbing/Gas - Water Pipe
Gang Bath Water ,llines
Rescheduled 1/17/2024:Electrical - 1st Underground Rough–In
Also Driveway Foundations
Passed: Plumbing/Gas - 2nd Rough-In
120 Psi Test
Passed: Fire - Aboveground Sprinkler - Visual (On Site)
Passed: Electrical - Above Ceiling
Passed: Building - Final
Passed: Fire - Fire Final
Inspected by Cpt. Shane Overstreet
Smoking Pavilion Footers
Four Areas Complete
Passed: Fire - Operational Test - Sprinkler/Standpipe
Checked On 6/21/24 All In Working Order.
Rescheduled 7/11/2024:Building - Final