Permit Details

Permit Search

Permit

New Commercial Construction

211 NE MCCLOSKEY AVE
LAKE CITY, FL 32055

Permit #
000047870
Application #
61485
Status Completed
  1. Submitted Jun 8, 2023
  2. Issued Aug 10, 2023
  3. Expires Jan 7, 2025
  4. Completed Jul 11, 2024

Property

Parcel #
07463-004
Owner
United States Cold Storage Inc Ferry Terminal Bldg,
Acres
36.72
Subdivision
—
Zoning
I
Flood zone
X
District
1

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0305D
This is the construction of a:
Phase 3 Expansion
Driveway access to property:
Existing Drive
Is there a Fire Sprinkler System?
Yes
Setbacks Front
20'
Setback Side 1
15'
Setback Side 2
15'
Setback Rear
15'
Describe commercial use:
Industrial / Cold Storage / Warehouse
Stories
1
Heated Area (Sqft)
101437
Total Area (Sqft)
101437
Building Height
60
Building Code Construction Type
II
Building Code Element
B
Occupancy Use Title
Moderate Hazard Storage and Business
Dev Permit #
F023-
Design Occupant Load
51
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Sealed roof decking options. (Must select one.)
Other (explain)
Service Amps
4000

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified
  4. Point Review - Printed-Online Application
  5. Plan Review - Plumbing Approved
  6. Plan Review - Mechanical Approved
  7. Plan Review - Electrical Approved
  8. Plan Review - Building Approved
  9. Plan Review - Reviewed
  10. Zoning Review - Reviewed
  11. Final Review - Documents Required
  12. Final Review - Documents Required
  13. Final Review - Documents Required
  14. Final Review - Documents Required
  15. Final Review - Processing
  16. Final Review - Reviewed
  17. Final Review - Payment Needed
  18. Permit Issued
  19. Final Review - Payment Needed
  20. Final Review - Payment Needed

Contractors

  • Gregory F Kitchens

    Siemens Industry Inc

    License
    EF0000711
    Title
    Cert. Alarm System
    Role
    Subcontractor

    County License & State License Expired.

  • David R Hardin

    Stellar Industrial Solutions, Inc

    License
    EC13012182
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License Expired.

  • Michael R Santarone

    Stellar Contraction, Inc

    License
    CGC042238
    Title
    Cert. General
    Role
    Contractor

    County License & State License & Employees Workers Comp Expired.

  • Justin R Mcneely

    Stellar Industrial Solutions, Inc

    License
    CMC1251158
    Title
    Cert. Mechanical
    Role
    Subcontractor

    County License & State License & Employees Workers Comp Expired.

  • Todd S Morgan

    Comprehensive Energy Services Inc

    License
    CFC043045
    Title
    Cert. Plumbing
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Aug 4, 2023

    Passed: Fire - Plan Review

    Inspected by Shane Overstreet

  2. Aug 11, 2023

    Passed: Building - Footer

    All Interiors Except For East Row

    Inspected by Troy Crews

  3. Aug 11, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  4. Aug 16, 2023

    Passed: Building - Footer

    5 Pier Footers East Side

    Inspected by Troy Crews

  5. Aug 16, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  6. Aug 18, 2023

    Passed: Building - Footer

    Ne 1/3 Of Permiter Foundation

    Inspected by Troy Crews

  7. Aug 18, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  8. Aug 22, 2023

    Passed: Building - Footer

    Peer Foundations At Existing Building

    Inspected by Troy Crews

  9. Aug 22, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  10. Aug 24, 2023

    Passed: Building - Footer

    Patrial East Side Perimiter And Partial North At Exiting Building Piers.

    Inspected by Troy Crews

  11. Aug 24, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  12. Aug 25, 2023

    Passed: Building - Footer

    Remainder Of East Side Perimiter With Pads, And North Pads At Existing Building.

    Inspected by Troy Crews

  13. Aug 25, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  14. Sep 5, 2023

    Passed: Building - Footer

    Piers At North Wall

    Inspected by Troy Crews

  15. Sep 5, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  16. Sep 7, 2023

    Passed: Building - Footer

    3 Interiors South End Wall South End

    Inspected by Troy Crews

  17. Sep 7, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  18. Sep 8, 2023

    Passed: Building - Footer

    Perimiter At Se Corner

    Inspected by Troy Crews

  19. Sep 8, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  20. Sep 11, 2023

    Passed: Building - Footer

    Remainder Of Perimeter Footing South End

    Inspected by Troy Crews

  21. Sep 11, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  22. Sep 19, 2023

    Passed: Fire - Plan Review

    Inspected by Shane Overstreet

  23. Sep 19, 2023

    Passed: Electrical - 1st Underground Rough–In

    North Side Parking Lot Conduits., Partial South Side.

    Inspected by Troy Crews

  24. Sep 25, 2023

    Passed: Electrical - 1st Underground Rough–In

    Parking Lot Rough In

    Inspected by Troy Crews

  25. Sep 27, 2023

    Passed: Building - Fire Rated Wall

    Tilt Wall Panels For South End

    Inspected by Troy Crews

  26. Oct 2, 2023

    Passed: Building - Slab

    Stair Landings East Side Of Building

    Inspected by Troy Crews

  27. Oct 4, 2023

    Passed: Building - Slab

    Stem Wall Pour East Side 3 Spots

    Inspected by Troy Crews

  28. Oct 4, 2023

    Passed: Electrical - 2nd Rough-In

    4 Bases 10 Ft Deep With Cage

    Inspected by Troy Crews

  29. Oct 6, 2023

    Passed: Electrical - 1st Underground Rough–In

    Light Bases

    Inspected by Troy Crews

  30. Oct 10, 2023

    Passed: Electrical - 2nd Rough-In

    Ligh Base Conduits.

    Inspected by Troy Crews

  31. Oct 19, 2023

    Passed: Building - Slab

    Sections Of Parking Lot

    Inspected by Troy Crews

  32. Nov 1, 2023

    Passed: Building - Footer

    Anchor Plates Bottom Of Tilt Wall Anchors Being Installed To Footer

    Inspected by Troy Crews

  33. Nov 1, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  34. Nov 16, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Drains For Fire Room And And Drain For Existing Compressor Room.

    Inspected by Troy Crews

  35. Nov 21, 2023

    Passed: Building - Masonry Wall Reinforcing

    Sump Pit Footer

    Inspected by Troy Crews

  36. Nov 21, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Drains For Commpresors

    Inspected by Troy Crews

  37. Nov 29, 2023

    Passed: Building - Monolithic Slab

    Compressor Room Slab

    Inspected by Troy Crews

  38. Nov 29, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  39. Dec 5, 2023

    Passed: Building - Slab

    Last Parking Lot And Slab For Railroad Car

    Inspected by Troy Crews

  40. Dec 8, 2023

    Passed: Building - Footer

    Loading Dock Stairs, Walls

    Inspected by Troy Crews

  41. Dec 8, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  42. Dec 13, 2023

    Passed: Building - Slab

    1 St Tie In From Parking Lot Toward Builing, Inside Slab E- Mail Pictures

    Inspected by Troy Crews

  43. Dec 15, 2023

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  44. Dec 18, 2023

    Passed: Fire - Plan Review

    Inspected by Cpt.shane Overstreet

  45. Dec 19, 2023

    Passed: Building - Slab

    Front Break Area

    Inspected by Troy Crews

  46. Jan 3, 2024

    Passed: Plumbing/Gas - Sanitary

    Gang Bath Area

    Inspected by Troy Crews

  47. Jan 4, 2024

    Passed: Building - Slab

    First Two Sections Of 10 Inch Slab

    Inspected by Troy Crews

  48. Jan 5, 2024

    Passed: Building - Insulation

    Gang Bath Hot Water Lines

    Inspected by Troy Crews

  49. Jan 12, 2024

    Passed: Building - Slab

    Inspected by Troy Crews

  50. Jan 12, 2024

    Passed: Plumbing/Gas - Water Pipe

    Gang Bath Water ,llines

    Inspected by Troy Crews

  51. Jan 16, 2024

    Rescheduled 1/17/2024:Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  52. Jan 17, 2024

    Passed: Electrical - 1st Underground Rough–In

    Also Driveway Foundations

    Inspected by Troy Crews

  53. Jan 17, 2024

    Passed: Plumbing/Gas - 2nd Rough-In

    120 Psi Test

    Inspected by Troy Crews

  54. Jan 18, 2024

    Passed: Plumbing/Gas - Water Pipe

    Inspected by Troy Crews

  55. Jan 22, 2024

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  56. Feb 9, 2024

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  57. Feb 22, 2024

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  58. Mar 12, 2024

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  59. Mar 21, 2024

    Passed: Fire - Aboveground Sprinkler - Visual (On Site)

    Inspected by Cpt.shane Overstreet

  60. Mar 22, 2024

    Passed: Electrical - Above Ceiling

    Inspected by Troy Crews

  61. May 1, 2024

    Passed: Building - Final

    Inspected by Troy Crews

  62. May 21, 2024

    Passed: Fire - Fire Final

    Inspected by Cpt. Shane Overstreet

  63. May 22, 2024

    Passed: Building - Footer

    Smoking Pavilion Footers

    Inspected by Troy Crews

  64. May 22, 2024

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  65. May 22, 2024

    Passed: Building - Final

    Four Areas Complete

    Inspected by Troy Crews

  66. Jun 21, 2024

    Passed: Building - Final

    Inspected by Cpt. Shane Overstreet

  67. Jun 21, 2024

    Passed: Fire - Fire Final

    Inspected by Cpt. Shane Overstreet

  68. Jun 21, 2024

    Passed: Fire - Operational Test - Sprinkler/Standpipe

    Checked On 6/21/24 All In Working Order.

    Inspected by Cpt. Shane Overstreet

  69. Jul 8, 2024

    Rescheduled 7/11/2024:Building - Final

    Inspected by Troy Crews

  70. Jul 11, 2024

    Passed: Building - Final

    Inspected by Troy Crews