7/6/2023
|
Point Review - Received-Hard Copy Application
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* STUP APPROVAL
* 911 ADDRESS
|
7/6/2023
|
Point Review - Reviewed
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* STUP APPROVAL
* 911 ADDRESS
|
7/10/2023
|
Plan Review - Reviewed
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* STUP APPROVAL
* 911 ADDRESS
|
7/10/2023
|
Zoning Review - Reviewed
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* STUP PAYMENT - INVOICE SENT TO SONYA ON 7/6/23
* 911 ADDRESS
**THERE IS A SIGNIFICANT DIFFERENCE IN THE ELEVATION AT THE ROAD AND THE ELEVATION AT THE PROPOSED HOME SITE. IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
7/11/2023
|
Final Review - Documents Required
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* 911 ADDRESS
**THERE IS A SIGNIFICANT DIFFERENCE IN THE ELEVATION AT THE ROAD AND THE ELEVATION AT THE PROPOSED HOME SITE. IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
7/14/2023
|
Final Review - Documents Required
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* 911 ADDRESS
**THERE IS A SIGNIFICANT DIFFERENCE IN THE ELEVATION AT THE ROAD AND THE ELEVATION AT THE PROPOSED HOME SITE. IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
7/24/2023
|
Final Review - Documents Required
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
**THERE IS A SIGNIFICANT DIFFERENCE IN THE ELEVATION AT THE ROAD AND THE ELEVATION AT THE PROPOSED HOME SITE. IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
7/24/2023
|
Final Review - Documents Required
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
**THERE IS A SIGNIFICANT DIFFERENCE IN THE ELEVATION AT THE ROAD AND THE ELEVATION AT THE PROPOSED HOME SITE. IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
7/27/2023
|
Final Review - Documents Required
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
**THERE IS A SIGNIFICANT DIFFERENCE IN THE ELEVATION AT THE ROAD AND THE ELEVATION AT THE PROPOSED HOME SITE. IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
8/3/2023
|
Final Review - Documents Required
NEEDED
**THERE IS A SIGNIFICANT DIFFERENCE IN THE ELEVATION AT THE ROAD AND THE ELEVATION AT THE PROPOSED HOME SITE. IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
LIDAR INDICATES SITE IS 6 FT. BELOW RD.
|
8/4/2023
|
Final Review - Reviewed
**THERE IS A SIGNIFICANT DIFFERENCE IN THE ELEVATION AT THE ROAD AND THE ELEVATION AT THE PROPOSED HOME SITE. IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
LIDAR INDICATES SITE IS 6 FT. BELOW RD.
|
8/4/2023
|
Final Review - Payment Needed
**THERE IS A SIGNIFICANT DIFFERENCE IN THE ELEVATION AT THE ROAD AND THE ELEVATION AT THE PROPOSED HOME SITE. IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
LIDAR INDICATES SITE IS 6 FT. BELOW RD.
|
8/4/2023
|
Permit Issued
Permit # created and approved from payment.
|
8/21/2024
|
Application Voided
This application was voided and not refunded
|