| 6/20/2023 |
Application pending. |
| 6/20/2023 |
Application submitted by applicant. |
| 6/28/2023 |
Point Review - Reviewed |
| 6/28/2023 |
Point Review - Printed-Online Application |
| 6/30/2023 |
Plan Review - Electrical Approved |
| 6/30/2023 |
Plan Review - Building Approved |
| 6/30/2023 |
Plan Review - Reviewed |
| 6/30/2023 |
Zoning Review - Documents Required |
| 7/3/2023 |
Zoning Review - Documents Required |
| 7/3/2023 |
Zoning Review - Documents Required |
| 7/5/2023 |
Zoning Review - Documents Required |
| 7/6/2023 |
Zoning Review - Corrections Needed |
| 7/6/2023 |
Final Review - Processing |
| 7/11/2023 |
Zoning Review - Reviewed |
| 7/11/2023 |
Final Review - Documents Required |
| 7/18/2023 |
Final Review - Payment Needed |
| 7/18/2023 |
Permit Issued |