3/29/2023
|
City of Lake City Notified of Application within City of Lake City LC_GAS, LC_WATER, LC_SEWER.
|
3/29/2023
|
Point Review - Received-Hard Copy Application
NEEDED
* UPDATED WORKERC COMP, LIABILITY, AND STATE LICESNE FOR DAVID SIMQUE - PLEASE UPLOAD THIS UNDER "OTHER"
* SIGNED SUB FORM FOR MICHAEL RAINBOLT
* COST BREAKDOWN OF MECHANICAL AND ELECTRICAL
* CITY OF LAKE CITY APPROVAL LETTER
|
3/29/2023
|
Point Review - Reviewed
NEEDED
* UPDATED WORKERC COMP, LIABILITY, AND STATE LICESNE FOR DAVID SIMQUE - PLEASE UPLOAD THIS UNDER "OTHER"
* SIGNED SUB FORM FOR MICHAEL RAINBOLT
* COST BREAKDOWN OF MECHANICAL AND ELECTRICAL
* CITY OF LAKE CITY APPROVAL LETTER
|
4/12/2023
|
Plan Review - Documents Required
NEEDED
* UPDATED WORKERC COMP, LIABILITY, AND STATE LICESNE FOR DAVID SIMQUE - PLEASE UPLOAD THIS UNDER "OTHER"
* SIGNED SUB FORM FOR MICHAEL RAINBOLT
* COST BREAKDOWN OF MECHANICAL AND ELECTRICAL
* CITY OF LAKE CITY APPROVAL LETTER
ANY STRUCTURAL NEEDED FOR USE OF EXISYING MEZZANINE?
COMPLIANCE WITH ACCESSIBILITY UPPER LEVEL ?
|
4/13/2023
|
Plan Review - Documents Required
NEEDED
* UPDATED WORKERC COMP, LIABILITY, AND STATE LICESNE FOR DAVID SIMQUE - PLEASE UPLOAD THIS UNDER "OTHER"
* SIGNED SUB FORM FOR MICHAEL RAINBOLT
* COST BREAKDOWN OF MECHANICAL AND ELECTRICAL
* CITY OF LAKE CITY APPROVAL LETTER
ANY STRUCTURAL NEEDED FOR USE OF EXISYING MEZZANINE?
COMPLIANCE WITH ACCESSIBILITY UPPER LEVEL ?
|
4/24/2023
|
Plan Review - Documents Required
NEEDED
* UPDATED WORKERC COMP, LIABILITY, AND STATE LICESNE FOR DAVID SIMQUE - PLEASE UPLOAD THIS UNDER "OTHER"
* SIGNED SUB FORM FOR MICHAEL RAINBOLT
* COST BREAKDOWN OF MECHANICAL AND ELECTRICAL
* CITY OF LAKE CITY APPROVAL LETTER
ANY STRUCTURAL NEEDED FOR USE OF EXISTING MEZZANINE?
COMPLIANCE WITH ACCESSIBILITY UPPER LEVEL ?
|
4/25/2023
|
Plan Review - Documents Required
NEEDED
* UPDATED WORKERC COMP, LIABILITY, AND STATE LICESNE FOR DAVID SIMQUE - PLEASE UPLOAD THIS UNDER "OTHER"
* SIGNED SUB FORM FOR MICHAEL RAINBOLT
* COST BREAKDOWN OF MECHANICAL AND ELECTRICAL
* CITY OF LAKE CITY APPROVAL LETTER
ANY STRUCTURAL NEEDED FOR USE OF EXISTING MEZZANINE?
COMPLIANCE WITH ACCESSIBILITY UPPER LEVEL ?
|
5/2/2023
|
Plan Review - Documents Required
NEEDED
* UPDATED WORKERC COMP, LIABILITY, AND STATE LICESNE FOR DAVID SIMQUE - PLEASE UPLOAD THIS UNDER "OTHER"
* SIGNED SUB FORM FOR MICHAEL RAINBOLT
* COST BREAKDOWN OF MECHANICAL AND ELECTRICAL
* CITY OF LAKE CITY APPROVAL LETTER
ANY STRUCTURAL NEEDED FOR USE OF EXISTING MEZZANINE?
COMPLIANCE WITH ACCESSIBILITY UPPER LEVEL ?
|
5/8/2023
|
Plan Review - Documents Required
NEEDED
* UPDATED WORKERC COMP, LIABILITY, AND STATE LICESNE FOR DAVID SIMQUE - PLEASE UPLOAD THIS UNDER "OTHER"
* SIGNED SUB FORM FOR MICHAEL RAINBOLT
* COST BREAKDOWN OF MECHANICAL AND ELECTRICAL
* CITY OF LAKE CITY APPROVAL LETTER
ANY STRUCTURAL NEEDED FOR USE OF EXISTING MEZZANINE?
COMPLIANCE WITH ACCESSIBILITY UPPER LEVEL ?
|
5/25/2023
|
Plan Review - Documents Required
NEEDED
*MICAH RAINBOLT TO COMPLETE REGISTRATION
*CITY OF LAKE CITY APPROVAL LETTER
ANY STRUCTURAL NEEDED FOR USE OF EXISTING MEZZANINE?
COMPLIANCE WITH ACCESSIBILITY UPPER LEVEL?
IS SECOND FLOOR EXISTING?
|
6/7/2023
|
Plan Review - Electrical Approved
NEEDED
*MICAH RAINBOLT TO COMPLETE REGISTRATION
|
6/7/2023
|
Plan Review - Building Approved
NEEDED
*MICAH RAINBOLT TO COMPLETE REGISTRATION
|
6/7/2023
|
Plan Review - Reviewed
NEEDED
*MICAH RAINBOLT TO COMPLETE REGISTRATION
|
6/7/2023
|
Zoning Review - Reviewed
NEEDED
*MICAH RAINBOLT TO COMPLETE REGISTRATION
|
6/7/2023
|
Final Review - Processing
NEEDED
*MICAH RAINBOLT TO COMPLETE REGISTRATION
|
6/7/2023
|
Final Review - Documents Required
NEEDED
*MICAH RAINBOLT TO COMPLETE REGISTRATION-- AND SIGN ELECTRICAL SUB FORM-- FORM IS FILLED OUT WITH NO SIGNATURE
|
6/29/2023
|
Final Review - Reviewed
|
6/29/2023
|
Final Review - Payment Needed
|
6/29/2023
|
Permit Issued
Permit #000047569 created and approved.
|