| Passed: Engineering - Setbacks |
|
Gary Pitzer |
6/6/2023 |
| Passed: Building - Footer |
Steel And Electric Bond |
Gary Pitzer |
6/6/2023 |
| Electrical -1st Underground Rough–In |
Electric Conduit To Kitchen Island |
Gary Pitzer |
7/3/2023 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Drain Only, No Water Piping |
Gary Pitzer |
7/3/2023 |
| Passed: Building - Slab |
Steel Around Perimeter,plastic In Place And Taped, |
Gary Pitzer |
7/14/2023 |
| Passed: Building - Roof Decking |
|
Gary Pitzer |
9/5/2023 |
| Passed: Building - Wall Sheathing |
No Windows Or Doors |
Gary Pitzer |
9/5/2023 |
| Passed: Building - Framing |
|
Gary Pitzer |
10/4/2023 |
| Passed: Mechanical - Rough In |
|
Gary Pitzer |
10/25/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Gary Pitzer |
10/25/2023 |
| Failed: Electrical - 2nd Rough-In |
Outlet Placement Exceeds The Code In Several Locations |
Gary Pitzer |
10/25/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
12/26/2023 |
| Passed: Building - Insulation |
Foam Roofs D Batt Walls |
Gary Pitzer |
12/26/2023 |
| Septic Release Inspection |
|
Health Dept |
1/26/2024 |
| Passed: Electrical - Permanent Power |
|
Gary Pitzer |
2/23/2024 |
| Release to power company |
|
Gary Pitzer |
2/23/2024 |
| Passed: Engineering - Access Road/Driveway Right-of-Way Integrity Inspection |
|
Troy Crews |
4/12/2024 |
| Passed: Building - Final |
|
Troy Crews |
4/12/2024 |