2/7/2023
|
City of Lake City Notified of Application within City of Lake City LC_GAS, LC_WATER, LC_SEWER.
|
2/7/2023
|
Point Review - Received-Hard Copy Application
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
METAL BUILDING PLANS
COMPLETED SUB-VF WITH SIGNATURE FROM HARRY MOSELEY -HVAC
COMPLETED SUB-VF WITH SIGNATURE FROM LUCIOUS GEORGE - ROOFING
MANUAL J, ENERGY CALCS, BREAKOUT OF ELECTRICAL, PLUMBING, & HVAC
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
|
2/28/2023
|
Plan Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
COMPLETED SUB-VF WITH SIGNATURE FROM HARRY MOSELEY -HVAC
COMPLETED SUB-VF WITH SIGNATURE FROM LUCIOUS GEORGE - ROOFING
BREAKOUT OF ELECTRICAL, PLUMBING, & HVAC
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
SCANNING IN PLANS FOR FIRE DEPT. REVIEW 2-27-23
|
3/1/2023
|
Plan Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
COMPLETED SUB-VF WITH SIGNATURE FROM HARRY MOSELEY -HVAC
COMPLETED SUB-VF WITH SIGNATURE FROM LUCIOUS GEORGE - ROOFING
BREAKOUT OF ELECTRICAL, PLUMBING, & HVAC
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
SCANNING IN PLANS FOR FIRE DEPT. REVIEW 2-27-23
|
3/3/2023
|
Plan Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
COMPLETED SUB-VF WITH SIGNATURE FROM HARRY MOSELEY -HVAC
COMPLETED SUB-VF WITH SIGNATURE FROM LUCIOUS GEORGE - ROOFING
BREAKOUT OF ELECTRICAL, PLUMBING, & HVAC
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
SCANNING IN PLANS FOR FIRE DEPT. REVIEW 2-27-23
|
3/7/2023
|
Plan Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
COMPLETED SUB-VF WITH SIGNATURE FROM HARRY MOSELEY -HVAC
COMPLETED SUB-VF WITH SIGNATURE FROM LUCIOUS GEORGE - ROOFING
BREAKOUT OF ELECTRICAL, PLUMBING, & HVAC
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
SCANNING IN PLANS FOR FIRE DEPT. REVIEW 2-27-23
|
3/9/2023
|
Plan Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
COMPLETED SUB-VF WITH SIGNATURE FROM HARRY MOSELEY -HVAC
COMPLETED SUB-VF WITH SIGNATURE FROM LUCIOUS GEORGE - ROOFING
BREAKOUT OF ELECTRICAL, PLUMBING, & HVAC
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
SCANNING IN PLANS FOR FIRE DEPT. REVIEW 2-27-23
NEED FIRE DEPT. APPROVAL
|
3/13/2023
|
Plan Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
COMPLETED SUB-VF WITH SIGNATURE FROM HARRY MOSELEY -HVAC
COMPLETED SUB-VF WITH SIGNATURE FROM LUCIOUS GEORGE - ROOFING
BREAKOUT OF ELECTRICAL, PLUMBING, & HVAC
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
SCANNING IN PLANS FOR FIRE DEPT. REVIEW 2-27-23
NEED FIRE DEPT. APPROVAL
|
3/14/2023
|
Plan Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
COMPLETED SUB-VF WITH SIGNATURE FROM HARRY MOSELEY -HVAC
COMPLETED SUB-VF WITH SIGNATURE FROM LUCIOUS GEORGE - ROOFING
BREAKOUT OF ELECTRICAL, PLUMBING, & HVAC
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
SCANNING IN PLANS FOR FIRE DEPT. REVIEW 2-27-23
NEED FIRE DEPT. APPROVAL
|
3/15/2023
|
Plan Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
COMPLETED SUB-VF WITH SIGNATURE FROM HARRY MOSELEY -HVAC
COMPLETED SUB-VF WITH SIGNATURE FROM LUCIOUS GEORGE - ROOFING
BREAKOUT OF ELECTRICAL, PLUMBING, & HVAC
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
SCANNING IN PLANS FOR FIRE DEPT. REVIEW 2-27-23
NEED TO ADDRESS FIRE DEPT. COMMENTS
|
3/17/2023
|
Plan Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
SCANNING IN PLANS FOR FIRE DEPT. REVIEW 2-27-23
NEED TO ADDRESS FIRE DEPT. COMMENTS
|
3/20/2023
|
Plan Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
SCANNING IN PLANS FOR FIRE DEPT. REVIEW 2-27-23
NEED TO ADDRESS FIRE DEPT. COMMENTS
|
3/20/2023
|
Plan Review - Plumbing Approved
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
3/20/2023
|
Plan Review - Mechanical Approved
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
3/20/2023
|
Plan Review - Electrical Approved
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
3/20/2023
|
Plan Review - Building Approved
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
3/20/2023
|
Plan Review - Reviewed
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
3/20/2023
|
Zoning Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DRIVEWAY ACCESS - THROUGH CITY PUBLIC WORKS
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
4/6/2023
|
Zoning Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
4/10/2023
|
Zoning Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
4/12/2023
|
Zoning Review - Documents Required
LUCIOUS:
NEEDED:
CITY OF LAKE CITY APPROVAL LETTER - STAFF SPOKE WITH ROBERT ANGELO ON 2.1.23
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
4/25/2023
|
Zoning Review - Reviewed
LUCIOUS:
GEORGE WORKERS COMP
NEEDED:
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
4/25/2023
|
Final Review - Documents Required
LUCIOUS:
GEORGE WORKERS COMP
NEEDED:
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
5/2/2023
|
Final Review - Documents Required
LUCIOUS:
GEORGE WORKERS COMP
NEEDED:
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
5/8/2023
|
Final Review - Payment Needed
LUCIOUS:
GEORGE WORKERS COMP
NEEDED:
DOORS AND FIRE EXTINGUISHERS TO BE HANDLED DURING CONSTRUCTION PER MR. GEORGE 3-20-23
|
5/23/2023
|
Permit Issued
Permit #000047298 created and approved.
|