Communications Tower
Permit
| Application #: | 61060 |
| Permit #: |
000047295 |
| Related Permit: |
|
| Submitted: | Wednesday, May 3, 2023 |
| Issued: | Monday, May 22, 2023 |
| Expires: | Tuesday, April 2, 2024 |
| Completed: | Tuesday, April 2, 2024 |
| Status: |
Completed |
| Septic Release? |
N/A |
Job Details
| Finished floor requirement |
|
| Fema map number |
12023C0182D |
| This is the construction of a: |
THE PROPOSED PROJECT INCLUDES INSTALLING EQUIPMENT CABINETS ON A PROPOSED CONCRETE PAD INSIDE A 10' X15' GROUND SPACE WITHIN THE EXISTING COMPOUND, AND INSTALLING NEW EQUIPMENT AND MOUNTS ON THE EXISTING TOWER. |
| Select access to property: |
Existing Drive |
| Total Estimated Cost |
20000 |
| Tower Height |
309.71 |
| Building Code Edition |
2020 Florida Building Code 7th Edition and 2017 National Electrical Code |
| Is this a new or existing tower? |
Existing |
| Service Amps |
200 |
Review Notes
| 5/3/2023 |
Application pending. |
| 5/3/2023 |
Application submitted by applicant. |
| 5/11/2023 |
Point Review - Printed-Online Application |
| 5/11/2023 |
Point Review - Reviewed |
| 5/22/2023 |
Plan Review - Building Approved |
| 5/22/2023 |
Plan Review - Reviewed |
| 5/22/2023 |
Zoning Review - Reviewed |
| 5/22/2023 |
Final Review - Processing |
| 5/22/2023 |
Final Review - Reviewed |
| 5/22/2023 |
Final Review - Payment Needed |
| 5/22/2023 |
Permit Issued |
| 11/6/2023 |
Final Review - Payment Needed |
| 11/6/2023 |
Final Review - Payment Needed |
| 11/8/2023 |
Final Review - Payment Needed |
Contractors
| Name / Business |
License |
Title |
Role |
Larry Sweatt Ericsson Inc
|
CGC1532010 |
Cert. General |
Contractor |
Frank Kisel Ericsson Inc
County License & State License Expired. |
EC13009490 |
Cert. Electrical |
Subcontractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Passed: Electrical - 1st Underground Rough–In |
This Is For Electrical Conduit In Bottom Of Footing |
Matt Forsyth |
11/13/2023 |
| Cancelled: Electrical - Permanent Power |
|
Troy Crews |
11/14/2023 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
11/14/2023 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
11/14/2023 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
12/1/2023 |
| Release to power company |
|
Troy Crews |
12/1/2023 |
| Release to power company |
|
Troy Crews |
1/10/2024 |
| Passed: Culvert - Access Road/Driveway Right-of-Way Integrity Inspection |
|
Troy Crews |
4/2/2024 |
| Passed: Engineering - Zoning Final |
|
Troy Crews |
4/2/2024 |
| Cancelled: Building - Slab |
|
Troy Crews |
4/2/2024 |
| Cancelled: Engineering - Setbacks |
|
Troy Crews |
4/2/2024 |
| Cancelled: Building - Footer |
|
Troy Crews |
4/2/2024 |
| Passed: Building - Final |
|
Troy Crews |
4/2/2024 |