Permit Details

Permit Search

Permit

New Commercial Construction

4289 NW AMERICAN LN
LAKE CITY, FL 32055

Permit #
000047187
Application #
60511
Status Completed
  1. Submitted Mar 17, 2023
  2. Issued May 10, 2023
  3. Expires Oct 23, 2024
  4. Completed Apr 29, 2024

Property

Parcel #
02461-512
Owner
Terrel David C Jr Aprn Pa,
Acres
1.38
Subdivision
Plantation Village
Zoning
—
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Elevation regulation
Site & Development Plan
Finished floor requirement
161.96'
Requirement needed
By Nailing Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
Yes
Fema map number
12023C0290D
This is the construction of a:
Medical Office
Driveway access to property:
Private Road
Is there a Fire Sprinkler System?
No
Setbacks Front
20
Setback Side 1
10
Setback Side 2
10
Setback Rear
15
Describe commercial use:
Medical office
Stories
2
Heated Area (Sqft)
5745
Total Area (Sqft)
5885
Building Height
28
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Business
Occupancy Use Title
medical office
Dev Permit #
F023-
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Sealed roof decking options. (Must select one.)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
400

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City
  4. Point Review - Printed-Online Application
  5. Point Review - Reviewed
  6. Plan Review - Documents Required
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - Documents Required
  10. Plan Review - Documents Required
  11. Plan Review - Documents Required
  12. Plan Review - Documents Required
  13. Plan Review - Documents Required
  14. Plan Review - Plumbing Approved
  15. Plan Review - Mechanical Approved
  16. Plan Review - Electrical Approved
  17. Plan Review - Building Approved
  18. Plan Review - Reviewed
  19. Zoning Review - Documents Required
  20. Zoning Review - Documents Required
  21. Zoning Review - Documents Required
  22. Zoning Review - Reviewed
  23. Final Review - Reviewed
  24. Final Review - Reviewed
  25. Final Review - Payment Needed
  26. Permit Issued

Contractors

  • Kevin L Bedenbaugh Jr

    Plumb Level Construction Co Llc

    License
    CGC1516042
    Title
    General Contractor
    Role
    Contractor
  • Kevin L Bedenbaugh Jr

    Plumb Level Construction Co Llc

    License
    CCC1329482
    Title
    Roofing Contractor
    Role
    Subcontractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Ryan Felknor

    Felknor Electric, Inc.

    License
    EC13003153
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor

Inspections

  1. Mar 27, 2023

    Failed: Fire - Plan Review

    Need Clarification On The Upstairs Area. Throughout The Plans It States It's An Upstairs Office Area And On E 2 It States It's An Apartment And Entertainment Area, Which Will Change The Occupancy Type.

    Inspected by Dwight Boozer

  2. Apr 19, 2023

    Passed: Fire - Plan Review

    Inspected by Dwight Boozer

  3. May 25, 2023

    Passed: Building - Footer

    Inspected by Troy Crews

  4. May 25, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Jun 20, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Waste Lines Only

    Inspected by Troy Crews

  6. Jul 5, 2023

    Passed: Building - Slab

    Need Termite Treatment Paperwork Job Also Needs Job Box.

    Inspected by Troy Crews

  7. Aug 3, 2023

    Rescheduled 8/3/2023:Building - Wall Sheathing

    Inspected by Troy Crews

  8. Aug 3, 2023

    Passed: Building - Wall Sheathing

    Inspected by Troy Crews

  9. Aug 16, 2023

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  10. Oct 18, 2023

    Cancelled: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  11. Oct 18, 2023

    Cancelled: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  12. Oct 18, 2023

    Passed: Building - Framing

    Inspected by Troy Crews

  13. Oct 18, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  14. Oct 18, 2023

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  15. Oct 18, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  16. Oct 27, 2023

    Failed: Building - Insulation

    Not Complete

    Inspected by Troy Crews

  17. Nov 2, 2023

    Passed: Building - Insulation

    Inspected by Troy Crews

  18. Jan 31, 2024

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  19. Jan 31, 2024

    Release to power company

    Inspected by Troy Crews

  20. Apr 25, 2024

    Passed: Fire - Fire Final

    Inspected by Joshua Wehinger

  21. Apr 26, 2024

    Certificate-Release Certificate

    Inspected by Troy Crews

  22. Apr 26, 2024

    Passed: Building - Final

    Inspected by Troy Crews

Documents