| Inspection |
Notes |
Performed By |
Date |
| Passed: Building - Footer |
|
Anthony Aslan |
6/2/2023 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
6/2/2023 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Steel In Cells Not Tied |
Anthony Aslan |
6/30/2023 |
| Passed: Building - Slab |
|
Anthony Aslan |
7/18/2023 |
| Passed: Electrical - Temporary Service |
|
Anthony Aslan |
7/26/2023 |
| Release to power company |
|
Anthony Aslan |
7/26/2023 |
| Release to power company |
|
Melissa Garber |
8/7/2023 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
9/15/2023 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
9/15/2023 |
| Septic Release Inspection |
Septic Rec'd For Pool Only |
Health Dept |
12/13/2023 |
| Passed: Engineering - Spot Check |
Nailing Wall |
Anthony Aslan |
3/13/2024 |
| Passed: Building - Framing |
|
Anthony Aslan |
8/23/2024 |
| Passed: Building - Ext Strapping/Wall Sheathing |
Screws Used In Place Of Straps On Post |
Anthony Aslan |
8/23/2024 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
12/3/2024 |
| Passed: Mechanical - Rough In |
|
Anthony Aslan |
12/3/2024 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
12/3/2024 |
| Passed: Building - Insulation |
Walls Bid
attic Spray Foam |
Anthony Aslan |
12/30/2024 |
| Passed: Electrical - Permanent Power |
|
Anthony Aslan |
4/16/2025 |
| Release to power company |
|
Anthony Aslan |
4/16/2025 |
| Passed: Electrical - Permanent Power |
Pool Power Panel |
Anthony Aslan |
4/30/2025 |
| Release to power company |
House & Pool |
Anthony Aslan |
5/14/2025 |
| Passed: Building - Final |
Mark Is Uploading Final Termite And Blower Door Fresh Air Verified-- Assessments Owed-- Co To Be Issued Once Payment Rec'd-- 6.19.25 Mg |
Anthony Aslan |
6/18/2025 |