| Passed: Electrical - Temporary Service |
|
Anthony Aslan |
5/31/2023 |
| Release to power company |
|
Anthony Aslan |
5/31/2023 |
| Passed: Building - Footer |
|
Anthony Aslan |
6/15/2023 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
6/15/2023 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
7/13/2023 |
| Passed: Building - Slab |
|
Anthony Aslan |
7/24/2023 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
8/15/2023 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
8/15/2023 |
| Passed: Mechanical - Rough In |
Check For Fresh Air Mechanical Damper On Final Only Straight Duct To Front Porch As Of Now |
Troy Crews |
9/8/2023 |
| Passed: Electrical - 2nd Rough-In |
Need Framing Inspection Prior To Insulation |
Troy Crews |
9/8/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Need Framing Inspection Prior To Insulation |
Troy Crews |
9/8/2023 |
| Passed: Building - Framing |
|
Anthony Aslan |
9/11/2023 |
| Passed: Building - Insulation |
|
Anthony Aslan |
9/14/2023 |
| Passed: Engineering - Spot Check |
|
Troy Crews |
9/20/2023 |
| Passed: Engineering - Spot Check |
Met With Owner Regarding Shrinkage Cracks, Suggested Doing Flooring As Late As Possible In Process. |
Troy Crews |
9/25/2023 |
| Passed: Electrical - Permanent Power |
Need Septic Release |
Anthony Aslan |
12/26/2023 |
| Release to power company |
|
Melissa Garber |
1/3/2024 |
| Septic Release Inspection |
|
Health Dept |
1/3/2024 |
| Passed: Building - Final |
|
Anthony Aslan |
3/5/2024 |