Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

Additions Permit
Address 13700 S US HIGHWAY 441
LAKE CITY, FL 32025
Parcel #: 09562-000
Acres: 17.83
Owner: Love's Travel Stops & Country Stores Inc
Subdivision:
Zoning: CHI
Flood Zone: X
District: 4
Application #: 54684
Permit #: 000047110
Related Permit:
Submitted: Monday, September 12, 2022
Issued: Friday, January 26, 2024
Expires: Thursday, May 9, 2024
Completed: Thursday, May 9, 2024
Status: Completed
Septic Release? No
Notes:

Job Details
Is this an addition for commercial or residential use? Commercial
Description of addition: fuel canopy
Total Estimated Cost 500000
Heated Area (Sqft) 0
Total Area (Sqft) 7200
Stories 1
Building Height 45
Select driveway access to property: Existing Drive
Fire sprinklers? No
Dev Permit # F023-
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Fema map number 12023C0415C
Sealed roof decking options. (Must select one.) Other (explain)
Sealed roof decking explanation for other option. fuel canopy
Review Notes
5/5/2022 Application pending.
9/13/2022 Point Review - Printed-Online Application NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE SIGNED BY CORPORATE OFFICER AND CONTRACTOR (ONCE DETERMINED) *LETTER OF AUTHORIZATION FROM CONTRACTOR FOR JONI TO PULL PERMIT *CONTACT ZONING DEPT TO COMPLETE ZONING APPLICATION-- 386-719-1474-- JENNIFER DUBOSE
9/13/2022 Point Review - Reviewed NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE SIGNED BY CORPORATE OFFICER AND CONTRACTOR (ONCE DETERMINED) *LETTER OF AUTHORIZATION FROM CONTRACTOR FOR JONI TO PULL PERMIT *CONTACT ZONING DEPT TO COMPLETE ZONING APPLICATION-- 386-719-1474-- JENNIFER DUBOSE
11/7/2022 Plan Review - Documents Required NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE SIGNED BY CORPORATE OFFICER AND CONTRACTOR (ONCE DETERMINED) *LETTER OF AUTHORIZATION FROM CONTRACTOR FOR JONI TO PULL PERMIT *CONTACT ZONING DEPT TO COMPLETE ZONING APPLICATION-- 386-719-1474--
11/16/2022 Plan Review - Documents Required NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE SIGNED BY CORPORATE OFFICER AND CONTRACTOR (ONCE DETERMINED) *LETTER OF AUTHORIZATION FROM CONTRACTOR FOR JONI TO PULL PERMIT *CONTACT ZONING DEPT TO COMPLETE ZONING APPLICATION-- 386-719-1474--
12/14/2022 Plan Review - Documents Required NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE SIGNED BY CORPORATE OFFICER AND CONTRACTOR (ONCE DETERMINED) *LETTER OF AUTHORIZATION FROM CONTRACTOR FOR JONI TO PULL PERMIT *CONTACT ZONING DEPT TO COMPLETE ZONING APPLICATION-- 386-719-1474--
12/19/2022 Plan Review - Documents Required NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE SIGNED BY CORPORATE OFFICER AND CONTRACTOR (ONCE DETERMINED) *LETTER OF AUTHORIZATION FROM CONTRACTOR FOR JONI TO PULL PERMIT *CONTACT ZONING DEPT TO COMPLETE ZONING APPLICATION-- 386-719-1474--
1/3/2023 Plan Review - Documents Required NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE SIGNED BY CORPORATE OFFICER AND CONTRACTOR (ONCE DETERMINED) *LETTER OF AUTHORIZATION FROM CONTRACTOR FOR JONI TO PULL PERMIT *CONTACT ZONING DEPT TO COMPLETE ZONING APPLICATION-- 386-719-1474--
2/23/2023 Plan Review - Documents Required NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE SIGNED BY CORPORATE OFFICER AND CONTRACTOR (ONCE DETERMINED) *LETTER OF AUTHORIZATION FROM CONTRACTOR FOR JONI TO PULL PERMIT *CONTACT ZONING DEPT TO COMPLETE ZONING APPLICATION-- 386-719-1474--
3/8/2023 Plan Review - Documents Required NEEDED: *OWNER AND CONTRACTOR SIGNATURE PAGE SIGNED BY CORPORATE OFFICER AND CONTRACTOR (ONCE DETERMINED) *LETTER OF AUTHORIZATION FROM CONTRACTOR FOR JONI TO PULL PERMIT *CONTACT ZONING DEPT TO COMPLETE ZONING APPLICATION-- 386-719-1474--
3/30/2023 Plan Review - Documents Required NEED PLANS FOR CANOPY STRUCTURE AND FOOTINGS
4/3/2023 Plan Review - Documents Required NEED PLANS FOR CANOPY STRUCTURE AND FOOTINGS
4/5/2023 Plan Review - Documents Required NEED PLANS FOR CANOPY STRUCTURE AND FOOTINGS
4/12/2023 Plan Review - Building Approved
4/12/2023 Plan Review - Reviewed NEED PLANS FOR CANOPY STRUCTURE AND FOOTINGS
4/12/2023 Zoning Review - Reviewed NEED PLANS FOR CANOPY STRUCTURE AND FOOTINGS
4/12/2023 Final Review - Reviewed NEED PLANS FOR CANOPY STRUCTURE AND FOOTINGS
4/12/2023 Final Review - Documents Required ANY ELECTRICAL? WILL NEED SUB FORM FOR ELECTRICAL
5/2/2023 Final Review - Reviewed
5/2/2023 Final Review - Payment Needed
5/2/2023 Permit Issued Permit #000047110 created and approved.
1/19/2024 Final Review - Payment Needed
1/26/2024 Permit Reissued Permit reissued to reflect updated information.
1/31/2024 Plan Review - Reviewed
Contractors
Name/ Business License Title Role
Matthew Soride
Spatco Energy Solutions Llc
CBC1264756 Cert. Building Contractor
Matthew Soride
Spatco Energy Solutions Llc
EC13009926 Cert. Electrical Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer 4 X 6 Columns With Steel And Bolts Per Plan Troy Crews 1/31/2024
Passed: Engineering - Setbacks Troy Crews 1/31/2024
Passed: Building - Footer Grout At Anchor Bolts Troy Crews 4/4/2024
Passed: Engineering - Setbacks Troy Crews 4/4/2024
Passed: Electrical - 1st Underground Rough–In Power To Pumps Rough In Troy Crews 4/18/2024
Passed: Electrical - 1st Underground Rough–In Already Done On 4-18-24 Troy Crews 4/19/2024
Passed: Mechanical - Pipe Pressure Test Fuel Lines Pressure Test Troy Crews 4/26/2024
Passed: Building - Slab Troy Crews 5/1/2024
Passed: Building - Final Cpt .shane Overstreet 5/8/2024
Passed: Electrical - Permanent Power Cpt .shane Overstreet 5/8/2024
Passed: Fire - Fire Final Cpt .shane Overstreet 5/8/2024
Passed: Building - Final Troy Crews 5/9/2024