Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 472 SW MEADOW WOOD GLN
LAKE CITY, FL 32024
Parcel #: 00276-120
Acres: 4.96
Owner: Matukaitis Charles J, Matukaitis Beth A
Subdivision: Meadow Wood
Zoning: A-3
Flood Zone: X
District: 2
Application #: 59281
Permit #: 000047053
Related Permit:
Submitted: Wednesday, March 1, 2023
Issued: Monday, April 24, 2023
Expires: Friday, March 22, 2024
Completed: Friday, March 22, 2024
Status: Completed
Septic Release? Yes
Notes:
*HOME IS BEING BUILT ON LOT 10 **THE ELEVATION OF THE PROPOSED HOME SITE GREATLY EXCEEDS THE PLAT REQUIREMENT FOR MFE, THEREFORE WE WILL NOT REQUIRE A SURVEYOR LETTER TO CONFIRM THE ELEVATION.
Job Details
Elevation regulation Minimum Requirement
Finished floor requirement Bottom of lowest beam must be one foot above the road
Fema map number 12023C0401C
Mobile Home is a: Double Wide
Year Built 2025
Width (Ft.In) 24
Length (Ft.In) 50
Driveway access to home: Existing Drive
Installation Decal # 115994
Special temporary use permit number: STU250207
Septic # 25-0111
Setbacks Front 30'
Setback Side 1 25'
Setbacks Rear 25'
Dev Permit # F023-
Setback Side 2 25'
Are you applying for a 5 year temporary permit? Yes
Serial # FL265000HA000114AB
Wind Zone? 2
Residential or Commercial Use? Residential
Service Amps 200
How many of bedrooms does this home have? 3
How many bathrooms does this home have? 2
Review Notes
3/1/2023 Point Review - Received-Hard Copy Application
3/6/2023 Plan Review - Documents Required
3/13/2023 Plan Review - Documents Required
3/20/2023 Plan Review - Building Approved
3/20/2023 Plan Review - Electrical Approved
3/20/2023 Plan Review - Mechanical Approved
3/20/2023 Plan Review - Plumbing Approved
3/20/2023 Plan Review - Fuel/Gas Approved
3/20/2023 Plan Review - Reviewed
3/22/2023 Zoning Review - Reviewed
3/24/2023 Final Review - Documents Required
4/12/2023 Final Review - Documents Required
4/19/2023 Final Review - Reviewed
4/24/2023 Final Review - Payment Needed
4/24/2023 Permit Issued
12/11/2023 Final Review - Payment Needed
2/5/2024 Final Review - Payment Needed
2/7/2024 New address issued and ticket completed.
Contractors
Name/ Business License Title Role
Donald R Hollingsworth
Holly Electric Inc
EC13005429 Electrical Subcontractor
David E Hall
David Hall's Air Cond & Heating Svc,inc.
CAC057424 Class B A/c Contractor Subcontractor
Cody Barrs
Barrs Plumbing Inc
CFC1427145 Plumbing Contractor Subcontractor
Lewis G Walker
Lewis Walker Roofing Inc
CCC1333551 Cert. Roofing Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Plumbing/Gas - 1st Underground Rough–In Matt Forsyth 5/31/2023
Passed: Building - Footer Matt Forsyth 6/6/2023
Passed: Engineering - Setbacks Matt Forsyth 6/6/2023
Passed: Building - Slab Monolithic Slab Matt Forsyth 6/6/2023
Passed: Building - Roof Decking Matt Forsyth 7/7/2023
Passed: Building - Wall Sheathing Matt Forsyth 7/7/2023
Passed: Plumbing/Gas - 2nd Rough-In Water Heater Pan 1/12inches Off Floor Matt Forsyth 7/18/2023
Passed: Building - Framing Garage Doors And One Window On Backorder Matt Forsyth 7/21/2023
Passed: Building - Strapping Need To Finish Gable Straps Matt Forsyth 7/21/2023
Passed: Re-Roof - Final New Construction Matt Forsyth 7/21/2023
Passed: Mechanical - Rough In Matt Forsyth 8/2/2023
Passed: Electrical - 2nd Rough-In Matt Forsyth 8/2/2023
Passed: Building - Insulation Matt Forsyth 8/9/2023
Cancelled: Electrical - 2nd Rough-In Matt Forsyth 12/11/2023
Failed: Electrical - Permanent Power Work Not Complete Need Septic Release To Release Power Matt Forsyth 12/12/2023
Septic Release Inspection Health Dept 1/26/2024
Passed: Electrical - Permanent Power Parcel Matt Forsyth 2/5/2024
Release to power company Melissa Garber 2/7/2024
Rescheduled 3/22/2024:Building - Final Matt Forsyth 3/14/2024
Passed: Building - Final Matt Forsyth 3/22/2024